Key takeaways

  • The IMF-World Bank meetings in Bangkok put the ASEAN power grid back on the agenda after this year's Hormuz oil shock.
  • A grid cannot cut the oil bill quickly, but it lowers the cost of power for manufacturers and data centres once cross-border trade is priced and contracted.
  • We expect more money than megawatts in the next 18 months: financing will arrive before binding cross-border pricing does.

The shock has made the grid a finance topic

The IMF and World Bank annual meetings returned to Bangkok this week. Nikkei Asia reported that an Asian Development Bank executive and a Thai deputy prime minister urged faster progress on the regional grid, and that experts say Southeast Asia remains vulnerable to energy shocks, with high oil prices hitting businesses and households across the region.

The shock is recent. Brent crude hit $119 a barrel on 9 March 2026 after the Strait of Hormuz was disrupted, and was still above $105 in mid-May before easing to the low $70s by late June, according to AMRO. Governments reacted with price caps and subsidies, and the Philippines moved government offices to a four-day week, according to Investment Monitor.

The money is being assembled. The ADB launched a Regional Connectivity Fund for Energy in April with initial funding of $25bn, and a World Bank and ADB financing initiative launched in October 2025 estimates that up to $800bn of investment is needed by 2045.

Our view: the missing piece is price, not capital

Most coverage treats the grid as an engineering and funding problem. We think the binding constraint is commercial. Existing links are mostly bilateral or trilateral. The Laos-Thailand-Malaysia-Singapore project has operated since 2022 and lets up to 100MW of Lao power reach Singapore. That is a proof of concept, not a market.

A grid becomes a hedge only when a buyer in one country can sign a long-term contract with a seller in another, with agreed transit fees and shortage rules. Those terms are politically harder than building a cable, because each government protects its own tariffs and state utility.

Nor does a grid solve an oil shock directly: oil mostly fuels transport and industry. Its value is indirect, letting countries lean on each other's surplus and renewables. Governments that sell it as an instant fix will disappoint.

Who wins and who loses

The winners are buyers of reliable, large-scale power. The losers assumed the shock was temporary.

SegmentEffectWhy
Data centre operatorsGainWood Mackenzie projects regional data centre power demand rising from 2.6GW in 2025 to 10.7GW in 2035, so access to a wider supply pool matters
Energy-intensive manufacturersGain, slowlyLower and steadier power costs only follow once cross-border pricing is agreed
Renewable developers with surplus outputGainA regional grid widens the market beyond one national buyer
State utilities protecting local tariffsLose bargaining powerOpen cross-border trade exposes domestic pricing
Fuel-import-dependent economiesMixedThe grid reduces exposure over years, not months

What foreign companies should do

  • Treat grid integration as a five-to-ten-year option, not a basis for this year's site selection.
  • When choosing a site for power-hungry operations, ask for the interconnection plan and contract terms, not just the tariff.

What we expect

  1. Financing announcements for the regional grid will outpace signed multi-country power-trading contracts through 2027.

    By: end of 2027Watch: Whether any new agreement beyond the existing Laos-Thailand-Malaysia-Singapore link sets a transit fee and a shortage-sharing rule.

  2. Data centre developers, not governments, will be the first to sign long-term cross-border green power deals in the region.

    By: by mid-2028Watch: A disclosed power purchase agreement that crosses a national border for a data centre campus.

  3. Another oil spike will push governments back toward subsidies and coal before it pushes them toward the grid.

    By: within 12 months of any new Hormuz disruptionWatch: New fuel subsidy or price-cap announcements ahead of any grid commitment.

This is KIRA's view, based on the sources listed below.

Questions

Q: What is the ASEAN Power Grid?

A: It is a plan, launched in 1997, to connect national power systems across Southeast Asia, with regionally integrated grid operations targeted for 2045. Cross-border exchange exceeded 38,000 GWh between 2016 and 2022, according to AMRO.

Q: Will the ASEAN Power Grid lower electricity prices soon?

A: Not soon. Existing links are mostly bilateral or trilateral, and savings depend on cross-border pricing and contracts that governments have not yet settled.

Q: Why are the IMF and World Bank meetings relevant to energy?

A: This year's oil shock hurt businesses and households across Southeast Asia, so officials at the Bangkok meetings pressed for faster regional grid progress and financing.

Sources

  1. ASEAN power grid plan in spotlight at Bangkok IMF-World Bank meeting Nikkei Asia, 2026-10-15
  2. Iran energy shock spotlights regional grid ambitions in ASEAN Investment Monitor, 2026-04-30
  3. Asia's real energy test AMRO, 2026-07-16