Executive summary
Live data-centre IT capacity in 2030 by scenario
Vietnam · MW of operational IT load · ranges, not points · line = live capacity in Oct 2025
Source: [CBRE Nov 2025] for today; scenarios [Kira estimates]
Plan on the baseline of about 450 MW, but hold options for the AI corridor; the moves that pay in every future sit in power and equipment, not in halls.
BPL Aug 2026 = Doanh nhan & Phap luat · CBRE Nov 2025 = CBRE via VNA, DTiNews · G42 Feb 2026 = G42, FPT statements · TechNode Sep 2026 = TechNode Global · e-Conomy 2025 = Google, Temasek, Bain · Kira estimates = KIRA analyst triangulation
Vietnam has 104 MW of live IT load; Viettel and VNPT run 67 MW of it, and five players control 97%
Counts differ by scope: 104 MW is operational IT load [CBRE Nov 2025]; the ministry's 182 MW for March 2025 counts installed design capacity [MST Mar 2025].
Live IT capacity by operator
Vietnam · MW · October 2025
Source: [CBRE Nov 2025]; others = total less the two leaders [Kira estimates]
Data-centre facility types in Vietnam
Vietnam · 2026 · examples are illustrative, not complete
| Type | Examples | Direction |
|---|---|---|
| Telco colocation | Viettel IDC, VNPT IDC, FPT, CMC | Most of today's 104 MW; new hyperscale builds |
| Carrier-neutral colocation | STT VNG, NTT (building), StarMason (approved) | Foreign capital enters through JVs |
| Cloud and AI | FPT Smart Cloud, Viettel Cloud, AWS Local Zone | GPU halls; first hyperscaler zone |
| State | National Data Centre | Government data, live from Aug 2025 |
Source: [JLL Mar 2026]; [STT GDC May 2024]; [AWS Jun 2026]; [VNA Dec 2025]
The market is concentrated and state-led; a foreign entrant meets Vietnam's telcos as customers, partners and rivals at once.
AWS Jun 2026 = AWS Local Zone notice · CBRE Nov 2025 = CBRE via VNA, DTiNews · JLL Mar 2026 = JLL via VietNamNet · MST Mar 2025 = MST via VietNamNet · STT GDC May 2024 = STT GDC release · VNA Dec 2025 = VNA via DTiNews · Kira estimates = KIRA analyst triangulation
Why the range is wide but one-sided
Demand is not the brake. The digital economy grew 17% to USD 39 bn in 2025 [e-Conomy 2025]; G42 backs three AI and cloud sites with up to USD 1 bn of consumption commitments [G42 Feb 2026].
Power is. Data centres were moved to the business tariff, lifting bills by more than 50% [TechNode Sep 2026], and large sites must build their own 110 kV substations [BPL Aug 2026].
Paper runs ahead of halls. About 1.1 GW sits in named projects, but only about 0.2 GW is under construction [Kira estimates].