Executive summary

Installed solar capacity, today and in 2030
Brunei · MWp · 2024 and Aug 2026 actual; end-2026 build-up; 2030 KIRA base case; 2035 need
7202463Aug 2026121End-20262702030 base380-4902035 need
Source: [Hansard Aug 2026]; [Kira estimates] for end-2026, 2030 and the 2035 need

The answer in three lines

The fleet is real and growing fast. Capacity rose from 7 MWp in 2024 to 63 MWp by August 2026 and passes 100 MWp by end-2026 [Hansard Aug 2026]; projects already under way take it to about 120 MWp [Kira estimates].

Two buyers pay for it. The state buys under 25-year PPAs [Solarvest Jun 2025]; industrial owners build solar for their own plants [MoFE Feb 2026; Hibiscus Feb 2026].

2030 lands at 145-370 MWp depending on tender pace and captive build; 30% of capacity by 2035 needs roughly 380-490 MW [Kira estimates].

Treat Brunei as a small, lumpy but bankable market: enter through a local partner on state tenders and through industrial owners' own solar, not as a merchant developer.
Hansard Aug 2026 = LegCo answer PL297 · Hibiscus Feb 2026 = Business Today, Hibiscus · MoFE Feb 2026 = MoFE, SINAR release · Solarvest Jun 2025 = Solarvest Bursa filing · Kira estimates = KIRA analyst triangulation

Solar capacity rose ninefold in two years, from 7 MWp to 63 MWp, and passes 100 MWp when two plants finish at end-2026

The jump came from one refinery's rooftops and car parks, not from the grid.

How the solar fleet reaches about 120 MWp by end-2026
Brunei · MWp · build-up from 2024 to end-2026
72024+50SINAR stage 1+6Other63Aug 2026+46Belimbing+12Hibiscus121End-2026
Source: [Hansard Aug 2026]; [MoFE Feb 2026]; [Hibiscus Feb 2026]; [Kira estimates] for the split and the end-2026 total

A fast start from a small base

7 MWp to 63 MWp. The official count rose ninefold between 2024 and August 2026 [Hansard Aug 2026].

One project did most of it. Hengyi's SINAR stage 1 added over 50 MWp and 24 MWh of storage in February 2026 [MoFE Feb 2026].

Two more by year-end: Belimbing (46 MWp) and Hibiscus (12 MWp) are due to generate in 2026 [Hansard Aug 2026; Hibiscus Feb 2026].

Counting note: one international series still shows 6 MW at end-2025 [TaiyangNews Jun 2026]; we use the official answer, which includes captive plants.
Plan on a fleet of about 120 MWp at the start of 2027 and treat new capacity as arriving in 10-50 MWp blocks, not a steady flow.
Hansard Aug 2026 = LegCo answer PL297 · Hibiscus Feb 2026 = Business Today, Hibiscus · MoFE Feb 2026 = MoFE, SINAR release · TaiyangNews Jun 2026 = TaiyangNews · Kira estimates = KIRA analyst triangulation