Indonesia EV battery supply chain 2027: the nickel-to-cell vertical build-out

Indonesia holds 59% of global nickel supply but historically captured only the smelting margin. The 2026–2027 HPAL commissioning wave — three projects totalling approximately USD 8.6 bn in capex — converts Class 2 laterite into battery-grade Class 1 sulfate at Indonesian scale for the first time, moving an estimated USD 12–15 bn of annual value-chain revenue onshore. The June 2026 PPN DTP chemistry wedge (100% VAT relief for NMC vs 40% for LFP) and the January 2027 TKDN 60% step-up are the two policy gates that decide which OEMs access the incentive regime.

KIRA Research team

Indonesia's EV battery supply chain: the nickel-to-cell vertical build-out

Indonesia's EV battery supply chain is the most consequential industrial construction project in Southeast Asia this decade. The country holds 59% of global nickel supply [ESDM 2025] and 42% of proven reserves, but has historically exported almost entirely as Class 2 ferronickel and NPI — capturing the smelting margin while the battery-grade premium accrued to Japanese, Korean, and Chinese refiners. The 2026–2027 HPAL commissioning wave is the structural break: for the first time at scale, Indonesian laterite ore moves to battery-grade Class 1 sulfate onshore.

The four-layer value chain

The nickel-to-cell vertical spans four distinct value creation layers, each with different margin characteristics, different operators, and different timeframes to commercial scale.

Layer 1 — Mining and smelting (upstream). Indonesia operated 51 active smelters in 2024: 44 RKEF (rotary kiln electric furnace, producing ferronickel and NPI) and 7 HPAL (high-pressure acid leach, producing mixed hydroxide precipitate and nickel sulfate) [ESDM 2025]. Gross margin at the smelter gate runs 4–8% for ferronickel, 10% for HPAL/MHP output [Kira estimates from Kemenperin 2026]. Battery-grade Class 1 share of total nickel output rises from approximately 5% in 2024 to approximately 20% by 2027 as HPAL capacity comes online.

Layer 2 — Precursor and cathode active material (midstream). Precursor cathode active material (pCAM) is the value-multiplier step in the chain, delivering gross margins of approximately 14% [Kira estimates]. Morowali's integrated complex hosts the first commercial-scale pCAM lines in Indonesia [Kemenperin 2025]. The Gotion-ANEM HPAL project adds 120 kt per year of MHP capacity [Kontan 2025]. This is the layer with the longest lead time and the highest engineering risk; it is also the layer that was effectively absent from Indonesian production before 2024.

Layer 3 — Cell assembly (downstream, domestic). Two cell plants are in operation or near-commercial in 2026. The Hyundai–LG Energy Solution Karawang plant (10 GWh, commercial since July 2024) [Hyundai PR 2024] produces NMC cells for Hyundai's captive vehicle assembly. The CATL–IBC Karawang plant (6.9 GWh phase 1, targeted mid-2026) [CATL PR 2025] is an open-supply facility available to all TKDN-eligible OEMs. The KIRA team's base estimate puts combined installed capacity at approximately 32 GWh by 2027 [Kira estimates], including the planned Hyundai–LG phase 2 addition of 20 GWh [LGES 2025].

Layer 4 — Pack assembly and vehicle integration. OEM-level pack assembly runs at 8–12% blended gross margin under the 2026 TKDN regime [Kira estimates from company filings + Kemenperin 2026]. Battery cost per kWh fell from USD 149 in 2024 to a projected USD 80 by 2026 as domestic cells displace imports [Kemenperin 2026], with pack-level cost at 28–32% of vehicle bill of materials at current chemistry.

Smelter HPAL/MHP Precursor Cell assy BEV OEM 0% 5% 10% 15% 20% 6% 10% 14% 16% 10% Gross margin by value-chain segment · 2025–2027F · source: company filings, Kemenperin 2026, Kira estimates

The three HPAL projects that change the geometry

The 2026–2027 HPAL commissioning wave involves three projects with combined capex of approximately USD 8.6 bn [Kira estimates from project disclosures], all targeting Indonesian production of battery-grade nickel sulfate and MHP at a scale that has no precedent in the country's mining history.

Merdeka Battery Materials (MBMA) — 90 kt MHP line. MBMA disclosed its Q4 2025 high-purity nickel line targeting end-2026 commissioning [MBMA 2025]. The project is integrated within the broader Morowali industrial park and connects to existing RKEF ferronickel capacity. MBMA is publicly listed on the Indonesian Stock Exchange, providing quarterly production and commissioning updates.

Vale Indonesia–Ford–Huayou — Pomalaa, USD 4.5 bn. The three-way joint venture at Pomalaa (Sulawesi) targets nickel sulfate output for export to LG, Ford, and Huayou's downstream cell operations [Vale IR 2025]. The project brings international off-take commitments that de-risk the construction financing; it is the largest single HPAL investment in Indonesia to date.

BASF–Eramet — 67 kt nickel-cobalt refinery. The BASF–Eramet joint refinery targets battery-grade nickel and cobalt sulfate output, with BASF's European cathode operations as the primary downstream [Eramet 2025]. The project's integration with European battery supply chains creates a different commercial architecture from the Korean- and Chinese-oriented Morowali projects.

The KIRA team notes that Pomalaa and Morowali timing is likely to slip 1–2 quarters from current public guidance based on analyst reads [Kira estimates]. Off-take agreements signed pre-completion have historically commanded an 8–15% premium versus spot — the execution risk is real but the strategic logic remains compelling.

Chemistry choice: NMC vs LFP under the June 2026 incentive

The June 2026 PPN DTP scheme creates an explicit chemistry wedge in Indonesia's EV market — the first such policy in ASEAN. Nickel-based NMC cells and vehicles receive 100% VAT relief; non-nickel chemistries (primarily LFP imports from China) receive only 40% [Kemenkeu 2026]. This 1,400 basis-point incentive differential widens NMC's effective price advantage at retail by Rp 20–35m at the Rp 400–650m vehicle segment [Kira estimates].

The policy is explicitly designed to monetize Indonesia's nickel endowment downstream. It creates three categories of strategic response among OEMs. First, incumbents on NMC chemistry (Hyundai-Ioniq platform) benefit directly without factory changes. Second, LFP-dominant OEMs (BYD Blade, Wuling Air ev, Chery current models) face a structural incentive gap until they can switch chemistry or localise cell supply from the CATL-IBC open-supply facility. Third, OEMs without any local cell partnership lose TKDN eligibility at the 60% step-up in January 2027, facing both the incentive gap and import-tariff exposure simultaneously.

TKDN compliance: the local-content gate

Indonesia's local-content requirement ladder under Perpres 79/2023 defines three thresholds: 40% (2022–2026), 60% (2027–2029), and 80% (from 2030) [Sekneg 2023]. Kemenperin issued enforcement notices in August 2025 reminding BYD and peers to lock in compliance plans [Kompas 2025]. The penalty for shortfall is loss of PPN DTP incentive eligibility — not import bans — but the financial impact is equivalent given the scale of the VAT relief.

The 32 GWh of domestic cell capacity targeted by 2027 [Kira estimates] is sufficient to enable 60% TKDN for OEMs that establish supply relationships early. The constraint is not aggregate capacity but contractual access: BYD's Subang plant is designed to eventually switch from Chinese cell imports to domestic supply, but the transition requires lead-time agreements with CATL-IBC or an equivalent domestic supplier that must be signed well before the January 2027 TKDN step-up date.

Our analysts' structural view: the battery supply chain build-out is the deepest economic story in Indonesian industrialisation since the palm oil downstream expansion of the 2000s. The 2027 HPAL and cell-plant ramp creates onshore value capture that compresses the country's historical role as a raw material exporter. Whether that value accrues to Indonesian state entities, Korean-Chinese JV partners, or a new generation of domestic battery operators is the open strategic question for the remainder of the decade.

Sources: Battery-Tech 2026, CATL PR 2025, ESDM 2025, Eramet 2025, Hyundai PR 2024, Kemenkeu 2026, Kemenperin 2025 + 2026, Kompas 2025, Kontan 2025, LGES 2025, MBMA 2025, Sekneg 2023, Vale IR 2025, Kira estimates.