Key takeaways

  • BMI said on 9 October 2026 that rising costs, power constraints and stricter sustainability rules are raising development risk in Johor, even as it remains Malaysia's dominant hub.
  • Power, not land or demand, now decides who can build, which favours well-capitalised operators and markets that can sell clean power directly.
  • We expect Johor to keep growing but to lose its status as the default choice, with Thailand and Vietnam taking a larger share of new regional capacity.

Johor is full of ambition and short of power

On 9 October 2026, research firm BMI said investors are looking beyond Johor. In its Malaysia Data Centre Overview, it pointed to "saturation issues" and to rising costs, power constraints and stricter sustainability rules.

The scale is still large. Malaysia has 125 data centres with 925.6MW of live capacity, with 2GW under construction and 3.1GW planned, and Johor dominates that pipeline. But data centres made up about 20% of Malaysia's electricity demand growth in 2024 and should exceed 70% in 2026. Demand is growing about four times faster than renewable output, and grid expansion typically takes five to 10 years.

Cost is the second squeeze. BMI cites reported new tariffs on facilities above 100MW that have lifted energy costs by 10% to 14%, and says some operators have paused plans. Nearly 30% of proposed developments were rejected for not showing responsible power and water use.

Our view: the contest has moved from land to electrons

Most coverage frames this as Johor losing to its neighbours. We think that is too simple. Johor keeps its edge in proximity to Singapore, lower operating costs and better cross-border links.

What changes is where the marginal gigawatt goes. When a grid cannot add supply for five to 10 years, the scarce asset is a secured power contract, not a plot of land. Thailand has launched a 2GW direct power purchase pilot that lets eligible data centres buy renewable electricity straight from generators. Vietnam allows full foreign ownership and has simplified provincial licensing.

Indonesia shows the other risk. Batam is drawing AI investment, including a DayOne facility with a 511 MVA supply agreement, about 450MW. Yet a member of the DPR is already urging investors to help build infrastructure and create local jobs.

Who wins and who loses

BMI expects consolidation around well-capitalised, private equity-backed platforms. Power-rich and policy-friendly markets gain; speculative landbankers and thinly funded operators lose.

SegmentEffectWhy
Large platforms with secured power (BMI names DayOne, AirTrunk, Bridge Data Centres, Yondr)WinFinancing and dedicated power cope with higher upfront costs
Smaller operatorsLoseBMI says they may struggle to raise funds and keep up with infrastructure costs
ThailandWin2GW direct renewable power purchase pilot
VietnamWinFull foreign ownership and simpler provincial licensing
Landbankers in Johor without powerLoseLand is no longer the bottleneck; grid access is

What foreign companies should do

  • Secure the power contract before the land, and test it against the grid timeline of five to 10 years.
  • Model Johor tariffs at the higher post-revision level, not the old one.

What we expect

  1. Johor will remain Malaysia's largest data centre hub, but new regional announcements will tilt towards Thailand and Vietnam relative to Johor.

    By: by end-2027Watch: Share of newly announced capacity located in Thailand and Vietnam versus Johor in operator press releases and BMI updates.

  2. Thailand's direct power purchase pilot will become the template other Southeast Asian markets copy for data centres.

    By: by mid-2027Watch: A second market announcing direct renewable power sales to data centres, or Thailand widening the pilot.

  3. Smaller Johor operators will be bought by or merge into larger platforms.

    By: within 18 monthsWatch: Acquisitions of small Johor platforms by the large private equity-backed operators BMI names.

This is KIRA's view, based on the sources listed below.

Questions

Q: Is Johor still the best place for data centres in Southeast Asia?

A: It is still the largest, with the biggest pipeline in Malaysia and proximity to Singapore. For new large AI sites, power access and tariffs now matter more, and BMI says investors are looking at Thailand and Vietnam.

Q: Why are data centre investors looking beyond Johor?

A: BMI cites power constraints, higher costs from new tariffs on sites above 100MW, and stricter sustainability screening. Grid expansion typically takes five to 10 years.

Q: What makes Thailand and Vietnam more attractive?

A: Thailand has a 2GW pilot letting data centres buy renewable power directly from generators. Vietnam allows full foreign ownership and has simplified provincial licensing.

Sources

  1. Vietnam, Thailand gain appeal as data centre investors diversify beyond Johor Free Malaysia Today, 2026-10-09
  2. Batam AI Investment: DPR Urges Data Centers to Prioritize Local Workers Batam News Asia, 2026-10-13
  3. Malaysia risks investment in data centers fleeing after power hike shock w.media, 2025-07-01