Key takeaways
- On 2026-11-27 Johor said it had approved 21 MLD of treated water for 19 operating data centres, against 73 MLD they first sought.
- Treated water is now a scarce permit in Johor, and an operator's cooling and water-sourcing plan decides how fast it can grow.
- We expect reclaimed-water and dry-cooling designs to become the norm for new Johor approvals within the next year.
Johor gave data centres less than a third of the water they asked for
Winding up the Budget 2027 debate in the state assembly on 27 November 2026, Menteri Besar Onn Hafiz Ghazi said the state had approved 21 million litres a day (MLD) of treated water for the 19 data centres operating in Johor. Their first applications added up to 73 MLD. The approved volume is about 1.05% of Johor's average treated water output of 2,034 MLD.
He said water and energy security "cannot be compromised". Every application passes a technical check by a state coordination committee before planning permission.
In late 2025 Johor stopped approving less efficient Tier 1 and Tier 2 facilities; in July 2026 parliament was told new data centres need enough energy and water.
Water, not power, is becoming the binding permit
Most coverage reads the 1% figure as reassurance: data centres take a tiny share of the state's water. We read it the other way. The state is holding operators to that share by approving far less than they ask for, so the gap between 73 and 21 MLD has to be met by water the utility does not supply.
A BIMB Research note, reported on 1 January 2026, cited Ranhill SAJ's estimate that Johor needs roughly 1,000 MLD of new potable supply by 2030. New river schemes face slow approvals. Power can be contracted; new raw water takes years.
Leaders are already off the public network. Bridge Data Centres treats wastewater at a 5-million-litre-a-day plant in Ulu Tiram. Computility runs a 4-million-litre plant in Gelang Patah on 100% reclaimed water. DayOne draws up to 10 MLD from the polluted Sungai Tebrau and treats it itself.
Operators with their own water win; late potable-water projects lose
Treatment plants add capex and lead time, but in Johor the alternative is a smaller or slower approval.
| Segment | Effect | Why |
|---|---|---|
| Operators with reclaimed or river-water plants | Win | They grow without drawing on the capped treated-water allocation and match the state's stated preference |
| New entrants planning potable-water evaporative cooling | Lose | Their requested volumes are likely to be cut, which delays or shrinks capacity |
| Water treatment and membrane suppliers | Win | Each campus now needs its own plant for wastewater or raw river water |
| Liquid and closed-loop cooling vendors | Win | Lower water use per megawatt makes an application easier to pass |
| Ranhill SAJ and the state water bodies | Mixed | Less pressure on household supply, but reclaimed-water and surplus deals add new commercial roles |
What foreign companies should do
- Secure wastewater or raw-water rights before land.
- Size water requests close to real need.
- Budget for an on-site treatment plant and its testing from day one.
What we expect
Johor will make reclaimed or self-treated water a formal condition for new large data centre approvals rather than a recommendation.
More Johor operators will announce their own wastewater or river-water treatment plants, following Bridge Data Centres, Computility and DayOne.
Water-intensive projects will shift toward Malaysian states with more spare supply, even as Johor stays the largest cluster.
This is KIRA's view, based on the sources listed below.
Questions
Q: How much water do Johor data centres use?
A: Johor says it has approved 21 MLD of treated water for 19 operating data centres, about 1.05% of the state's average treated water output of 2,034 MLD. Their first requests totalled 73 MLD.
Q: Do Johor data centres use recycled water?
A: Some do. Bridge Data Centres and Computility cool with treated wastewater from Indah Water Konsortium, and DayOne treats raw water from Sungai Tebrau at its own plant.
Q: Is Johor stopping new data centres?
A: No, but it approves water case by case after a technical check, stopped approving less efficient Tier 1 and Tier 2 facilities in late 2025, and gives household supply priority.
Sources
- Johor MB: State reins in data centre water allocations, approves 21 MLD of 73 MLD sought Malay Mail, 2026-11-27
- Johor won't sacrifice people's wellbeing for data centre investments, says MB Onn Hafiz The Star, 2026-11-27
- Johor pushes data centres to use treated water from polluted rivers New Straits Times, 2026-11-05
- Johor data centres turn to recycled water The Star, 2026-07-23
- Johor data centre water demand to accelerate The Star, 2026-01-01