Executive summary

~3x
Growth in operating build-to-rent homes, end-2025 to 2030 (baseline)
From 12,600 homes [ProperEasy Aug 2026] to 36,000-41,000; the four futures span 28,000-50,000.
[Kira estimates]
Three reasons1. Supply is short to 2030 in every future [NHSAC Aug 2026]. 2. Rules now favour new rental supply over buying existing homes [ATO 2026]. 3. The cost of capital, not demand, sets the pace.
Operating build-to-rent homes
Australia · thousand apartments in operation · 2026E and 2030F baseline are estimates (dashed / range)
ACTUAL FORECAST 2.8k Start 2023 12.6k End 2025 16.6k End 2026E 38.5k 36-41k range ~3x end-2025 2030F base
Source: [ProperEasy Aug 2026] for 2023 and 2025; 2026E and 2030F [Kira estimates], 2026E adding [Knight Frank Q3 2025] completions
Plan on the baseline, enter beside a local developer-manager now, and keep large commitments behind the rate and policy signposts in chapter 5.
ATO 2026 = ATO, foreign buyers · Cotality Oct 2026 = Cotality HVI, Sep 2026 · Knight Frank Q3 2025 = Knight Frank, Q3 2025 · MSCI Jul 2026 = MSCI BTR index · NHSAC Aug 2026 = Supply Council, Aug 2026 · ProperEasy Aug 2026 = ProperEasy (Franklin St) · SQM Oct 2026 = SQM Research, Sep 2026 · TE Oct 2026 = Trading Economics · Kira estimates = KIRA analyst triangulation

Australia finished 180,500 homes in the year to June 2026, a quarter short of the 240,000-a-year Accord pace

The supply council now expects the 1.2 million target to be met in the December quarter 2030, 18 months late [NHSAC Aug 2026].

New homes started and completed vs the Accord pace
Australia · dwellings, four quarters to June 2026 · Accord pace = 1.2 million homes over five years
Accord pace needed 240,000 Dwellings started 204,440 Dwellings completed 180,500 -25% vs the pace
Source: [ABS BA Jun 2026]; pace [Kira estimates] from the 1.2 million target

Why the gap persists

The pipeline is full but slow. 244,000 dwellings were under construction in the March quarter 2026, the most since records began in 1984 [NHSAC 2026].

Apartments take longest. The average apartment finished in 2025-26 took about 29 months from start, the longest in the series [ABS BA Jun 2026].

Industry sees a bigger miss. Master Builders expects the Accord to fall 204,000 homes short [MBA 2026].

Undersupply is locked in to 2030 in every scenario; the investor question is who gets to build and own the homes, not whether demand exists.
ABS BA Jun 2026 = ABS Building Activity, Jun qtr 2026 · MBA 2026 = Master Builders forecast, 2026 · NHSAC 2026 = Supply Council, Mar 2026 · NHSAC Aug 2026 = Supply Council, Aug 2026 · Kira estimates = KIRA analyst triangulation