Section 03 · Executive Summary
The ambition is real, but the build run-rate is not
RUPTL 2025-2034 lifts planned renewable capacity from 20.9 GW to 52.9 GW including storage, with 42.6 GW of generation: solar 17.1 GW, hydro 11.7 GW, wind 7.2 GW, geothermal 5.2 GW [RUPTL 2025]. Yet the 2025 geothermal add was just 112.7 MW [ThinkGeo 2026] — roughly a fifth of the 500-600 MW/year the pathway implies. Demand is structural: MEMR forecasts 4.8-5.2% annual electricity-demand growth [MEMR 2025].
Procurement reform is the swing variable
MEMR Reg 5/2025 replaces the PPA provisions of MEMR 10/2017, adds a 30-year build-own-operate structure, sharpens risk allocation, and caps the procurement clock at 180 days for direct selection, 90 days for direct appointment [MEMR Reg 5/2025]. The reform attacks the binding constraint — not resource, but the time and bankability gap between award and financial close.