market analysisIndonesiarenewable-energy2026-06-025 min

Indonesia renewable energy 2026: policy framework, procurement reform, and the regulatory gate

Four regimes shape every awarded megawatt in Indonesia's renewable sector: MEMR Reg 5/2025 rebuilds the PPA and caps the procurement clock at 90–180 days, PerPres 112/2022 sets the geothermal tariff ceiling, the 40% TKDN rule gates local content, and the GREM facility shares exploration-failure loss. Together they decide whether the 73% IPP mandate converts into steel in the ground.

KIRA Research team

Indonesia renewable energy 2026: policy framework, procurement reform, and the regulatory gate

Four regimes shape every awarded megawatt in Indonesia’s renewable sector: MEMR Reg 5/2025 rebuilds the PPA and procurement clock, PerPres 112/2022 sets the geothermal tariff ceiling, the 40% TKDN rule gates local content, and the GREM de-risking facility shares exploration loss. Together they decide whether the 73% IPP mandate converts into steel in the ground.

Direct appointment clock
90DAYS
new statutory cap [MEMR Reg 5/2025]
Direct selection clock
180DAYS
new statutory cap [MEMR Reg 5/2025]
Geothermal tariff ceiling
9.76c/kWh
≤10 MW years 1-10 [PerPres 112/2022]
GREM de-risking pool
USD 272m
PISP + donor grants [World Bank 2019]

MEMR Regulation 5/2025 — the procurement reset

MEMR Reg 5/2025 is the most important policy move for Indonesia’s renewable build. It replaces the PPA provisions of MEMR 10/2017, adds a 30-year build-own-operate structure, sharpens risk allocation — assigning each risk to the party best able to manage it — and allows pre-COD share-transfer for financing [MEMR Reg 5/2025]. Crucially it caps the procurement clock at 180 days for direct selection and 90 days for direct appointment, and lets surplus geothermal energy be sold to PLN.

The reform attacks the binding constraint — not resource, but the time and bankability gap between award and financial close. Developers with shovel-ready feasibility, secured land, and pre-arranged debt convert the faster clock into first-mover COD slots. The question through 2026-2027 is whether the early tenders actually close inside the caps, and whether PPAs reach bankability — that single read will discriminate bull from base faster than any capacity number.

The PLN monopsony shapes every bid

Generation reaches ratepayers through a single offtaker — PLN. RUPTL 2025-2034 lifts the renewable plan from 20.9 GW to 52.9 GW including storage, with IPPs developing 73% [RUPTL 2025] — PLN cannot finance the gap alone. But single-buyer PPA terms, payment certainty, and curtailment risk are what developers underwrite, and that is precisely what MEMR Reg 5/2025 sets out to standardise.

The finance requirement is stark: meeting net-zero 2060 needs ~USD 16 bn/year of renewable investment against the USD 3 bn that flowed in 2015-2021 [WRI 2024]. The Just Energy Transition Partnership pledges USD 20 bn of concessional and private finance [WRI 2024]; disbursement pace and bankable-project supply — not the headline pledge — will decide its impact.

PROCUREMENT REFORM · 2025
MEMR Regulation 5/2025 — renewable PPA guidelines
Replaces the PPA provisions of MEMR 10/2017. Adds a 30-year build-own-operate scheme, structured risk allocation assigning each risk to the party best able to manage it, and pre-COD share-transfer for financing [MEMR Reg 5/2025]. Caps the procurement clock at 180 days for direct selection and 90 days for direct appointment, and lets surplus geothermal energy be sold to PLN.
SOURCE: MEMR REGULATION NO. 5 OF 2025 · JDIH ESDM · ASHURST / ORRICK ANALYSIS 2025
TARIFF CEILING · ACTIVE
PerPres 112/2022 geothermal tariff structure
Sets the highest benchmark price referenced in any geothermal work-area tender: 9.76 c/kWh × location factor for ≤10 MW and 9.41 c/kWh for 10-50 MW in years 1-10, stepping to 8.00-8.30 c/kWh for years 11-30 [PerPres 112/2022]. Geothermal uniquely allows tariff escalation — a concession other renewables do not get, reflecting its capital intensity.
SOURCE: PRESIDENTIAL REGULATION 112/2022 · AHP / LEXOLOGY ANALYSIS
LOCAL CONTENT · BINDING GATE
40% TKDN local-content requirement
Developers have struggled to meet the 40% TKDN threshold under the existing pricing scheme, and geothermal construction must be done by domestic construction firms [Hogan Lovells 2025]. The rule protects local industry but raises cost for foreign-technology-dependent projects — recent relaxations target exactly this friction. MEMR Reg 5/2025 also addresses TKDN treatment.
SOURCE: HOGAN LOVELLS TKDN RELAXATION NOTE 2025 · ARMA LAW TKDN FRAMEWORK
DE-RISKING · ACTIVE
GREM resource-risk-mitigation facility
The Geothermal Resource Risk Mitigation programme provides USD 150 m of PISP public-window funds plus USD 122.5 m of donor reimbursable grants [World Bank 2019], sharing exploration-failure cost so developers do not fully bear dry-hole risk. It converts geothermal’s binary payoff into an underwritable one — the practical key to mobilising private capital against a ~USD 30 m exploration programme at risk before resource is confirmed.
SOURCE: WORLD BANK GREM PROJECT 2019 · PT SMI · GI HUB CASE STUDY

The 2034 outlook: what the policy reset can deliver

The base case puts the geothermal fleet at ~4.0 GW by 2034 [Kira estimates] — above today’s 2.74 GW but short of the 7.9 GW cumulative the RUPTL implies. Three levers decide the path: procurement-clock execution (does the 90/180-day cap actually compress timelines?), TKDN friction (does local-content cost stall foreign-tech projects?), and transmission build (can the grid reach the resource?). Each can move the 2034 number by 0.5-1.5 GW.

The bull case — reform lands, TKDN relaxed for specialist drilling tech, JETP capital flows, transmission keeps up — puts the fleet near ~5.5 GW by 2034 [Kira estimates] at a run-rate of 350-400 MW/year. The bear case, where reform under-delivers and TKDN stalls foreign-tech projects, leaves the fleet at ~3.3 GW at near-historical run-rate. The strategic bottom line: geothermal remains structurally scarce firm-clean baseload regardless of scenario. Sequence capital to the 2030-2034 window, partner with reserve-holding incumbents, and underwrite the exploration wall through GREM — not around it.

Geothermal fleet: history + 2034 scenarios
GW · 2024-2034 · base / bull / bear vs target
GW
0 2 4 6 8 4.0 Base 5.5 Bull 3.3 Bear 7.9 RUPTL 2024 2025 2029 2034
SOURCE: THINKGEOENERGY 2026, RUPTL 2025-2034, IDX CHANNEL 2025, KIRA TRIANGULATION · KIRA RESEARCH 2026
SOURCE KEY · Ember 2025 = Ember Indonesia electricity review 2025 · Hogan Lovells 2025 = Hogan Lovells Indonesia local-content (TKDN) relaxation note 2025 · IDX Channel 2025 = IDX Channel RUPTL 2025-2034 geothermal coverage Dec-2025 · MEMR Reg 5/2025 = MEMR Regulation No. 5 of 2025 (Renewable PPA Guidelines) · PerPres 112/2022 = Presidential Regulation 112/2022 on Renewable Acceleration · RUPTL 2025 = PLN Electricity Supply Business Plan 2025-2034 · ThinkGeo 2026 = ThinkGeoEnergy Indonesia Geothermal Update 2026 · World Bank 2019 = World Bank Geothermal Resource Risk Mitigation (GREM) Project · WRI 2024 = World Resources Institute Indonesia clean-energy investment study 2024 · Kira estimates = KIRA in-house analyst triangulation