Executive Summary
The PPA pivot is structural
Decree 135/2024/NĐ-CP enabled commercial-scale direct power purchase agreements between rooftop solar operators and industrial off-takers, effective November 2024 [MOIT 2024]. For the first time, a factory or industrial park tenant can contract multi-year solar supply at a negotiated tariff without routing through EVN's retail price schedule. The first signed DPPAs are priced at VND 1,450-1,700/kWh — a 15-25% discount to the industrial retail tariff [Kira estimates from developer conversations].
Grid is the ceiling, not demand
Vietnam's south-central solar corridor — Ninh Thuan, Binh Thuan, Khanh Hoa — generated more solar power than the 500kV backhaul to Hanoi and HCMC could absorb in 2024-25 [NLDC 2025]. Curtailment rates peaked at ~25% in Q2 2025 [NLDC 2025]. EVN's 500kV third-circuit extension (Đà Nẵng to Pleiku) and the 220kV reinforcements in the south are scheduled for 2026-27 completion, but grid timing, not project demand, decides when the next GW of utility-scale capacity becomes economically viable.
PDP8 sets 73.4 GWp by 2030 — DPPA unlocks the merchant layer
Power Development Plan VIII (Decision 500/QĐ-TTg, May 2023) set Vietnam's first legally binding solar installation target: 73.4 GWp by 2030 and 168-189 GWp by 2050 [PDP8 2023]. Decree 135/2024 activated the direct commercial PPA channel that makes reaching those targets without state-financed EVN procurement financially feasible.
PDP8 solar targets
PDP8 disaggregates the 73.4 GWp target: ~50 GWp utility-scale ground-mounted (mainly south-central and the Mekong delta) and ~23 GWp rooftop solar (commercial, industrial, and residential) [PDP8 2023]. Vietnam's base case as of end-2025 sits at 20.7 GWp installed — roughly 28% of the 2030 target with five years remaining [EVN 2025]. The gap is real but arithmetically achievable if transmission investment tracks.
Decree 135/2024 — the commercial PPA pivot
Decree 135/2024/NĐ-CP (November 2024) enables direct power purchase agreements between renewable energy generators and corporate off-takers, without requiring EVN as intermediary [MOIT 2024]. Eligible projects include rooftop solar (any capacity), ground-mounted solar below specified thresholds, and co-located battery storage. The decree resolves a 5-year legal limbo where RE100-committed FDI manufacturers could not legally contract private solar supply.
AUCM mechanism for utility-scale
The competitive auction mechanism (AUCM) governs grid-connected utility-scale solar above the DPPA threshold. Two pilot auction rounds (2025-26) allocated ~3.2 GW at clearing prices between VND 1,644-1,900/kWh [MOIT 2025] — roughly 7-8 US¢/kWh, competitive with regional peers but contingent on grid-interconnection agreement (GIA) availability. GIA issuance is the bottleneck: EVN's queue exceeds available transmission slots by ~2:1 [Kira estimates from EVN grid planning docs].