Executive summary

Transmission-level data centre power: requested, agreed, building and live
Taiwan · MW · Taipower data at 31 Jul 2026 · contracted capacity, not measured load
Requested, Jul 2026 (75)4,523 MWAgreed, Jul 2026 (47)3,331 MWUnder construction (5 sites)567 MWLive, contracted (4 sites)303.5 MWLive = 7% of requested MW
Source: [Taipei Times Aug 2026]; [Kira estimates]

The answer in three lines

The market is small but growing fast. We put third-party colocation revenue at NT$9-11 bn in 2025 and installed IT capacity at 260-330 MW [Kira estimates]; data centre power use doubled from 2021 to 2025 [Reporter Apr 2026].

Power, not demand, is the limit. About 40% of agreed requests lapsed [Taipei Times Aug 2026], and Chunghwa Telecom with Chief Telecom holds 78% of IDC capacity [CTEE Aug 2026].

The open doors are power-side. Equipment, integration and powered campuses in central and southern Taiwan are open to a foreign firm; Taipei retail colocation is not [Kira estimates].

Lead with what makes a megawatt usable, power gear and AI-ready fit-out, and treat a campus stake as a second step on a site that already has supply.
CTEE Aug 2026 = Commercial Times · Reporter Apr 2026 = The Reporter · Taipei Times Aug 2026 = Taipei Times · Kira estimates = KIRA analyst triangulation · full citations in Methodology and sources

Data centre power use doubled from 2021 to 2025; we put installed IT capacity at 260-330 MW

Power use is the only national series; we turn it into capacity with the typical efficiency and fill rate of a hall.

Electricity used by internet portal services and data centres
Taiwan · bn kWh a year · 2021 and 2025 · national statistics category
0.7320211.5020252.1x in four years, +20% a year
Source: [Reporter Apr 2026]
From power used to installed IT capacity, 2025
Taiwan · MW · bar = midpoint · 1.5 bn kWh ÷ 8,760 hours; utilisation 55-65%
Average power drawn, 2025171 MWIT load drawn (PUE 1.5)114 MWInstalled IT, stats category175-210 MWPlus telecom-run IDCs80-120 MWInstalled IT capacity, 2025260-330 MW
Source: [Kira estimates] from [Reporter Apr 2026]
Read 290 MW as the base to plan against: every new 25-80 MW campus moves the national total by a tenth or more.
Reporter Apr 2026 = The Reporter · Kira estimates = KIRA analyst triangulation · full citations in Methodology and sources