Executive summary

Installed offshore wind capacity, today and in 2030
Taiwan · GW · June 2026 actual; 2030 KIRA base case and official target
4.8Jun 20269.02030 base10.92030 target
Source: [MOEA Jun 2026]; [Enerdata 2025]; [Kira estimates] for the 2030 base case

The answer in three lines

A real market that roughly doubles. About 4.8 GW from 500 turbines was installed by June 2026 [MOEA Jun 2026]; awarded farms take it to about 9 GW by 2030, short of the 10.9 GW target [Enerdata 2025; Kira estimates].

Worth NT$45-55 bn a year in power sales, and NT$1.0-1.3 trn of new build to 2030 [Kira estimates]. Three sponsors hold about four-fifths of what is built.

The next round is thin. Round 3.3 drew two applications for at least 3.6 GW [NOWnews Sep 2026; MOEA Mar 2026].

Treat Taiwan as a large, open, execution-limited market: the money to 2030 is in supplying and co-owning awarded farms, not in winning new sea.
Enerdata 2025 = Enerdata · MOEA Jun 2026 = Energy Administration · MOEA Mar 2026 = MOEA · NOWnews Sep 2026 = NOWnews · Kira estimates = KIRA analyst triangulation

Installed capacity more than doubled from 2.25 GW to 4.8 GW in two and a half years

Growth has been fast, but every official date so far has slipped by one to two years.

Installed offshore wind capacity and official targets
Taiwan · GW · actuals at end-2023, end-2024 and June 2026; targets for 2030 and 2035 (low end)
2.25End-20233.04End-20244.80Jun 202610.902030 target18.302035 target
Source: [NRF 2024]; [MOEA Feb 2025]; [MOEA Jun 2026]; [Enerdata 2025]; [MOEA Jul 2026]

A fast build, a moving target

Doubled since end-2023. From 2.25 GW to 4.8 GW and 500 turbines by June 2026 [NRF 2024; MOEA Jun 2026]; about 4.9 GW by July [Enerdata Jul 2026].

World number five. Taiwan ranked fifth for installed offshore wind in 2025 and third for additions [MOEA Jun 2026].

Targets were cut, then stretched. 2030 fell from 13.1 GW to 10.9 GW [Enerdata 2025]; the 2026 roadmap sets 18.3-19.9 GW by 2035 and up to 27.9 GW by 2039 [MOEA Jul 2026].

So what: about 1-1.5 GW a year is the pace the supply chain has shown.
Size plans on about 1-1.5 GW of new capacity a year and discount official dates by a year or two.
Enerdata 2025 = Enerdata · Enerdata Jul 2026 = Enerdata · MOEA Feb 2025 = Energy Administration · MOEA Jul 2026 = MOEA offshore wind roadmap 2026-2039: 18.3-19.9 GW by 2035 · MOEA Jun 2026 = Energy Administration · NRF 2024 = Norton Rose Fulbright