LAOS · DATA CENTERS & CLOUD · MARKET ENTRY BRIEF

Laos data centres 2026: investment analysis

Does cheap power make a data centre pay in Laos, or do outages cancel the gain?

Executive summary

The tension: Laos exports most of its hydropower, while Vientiane clinics still report two to three power cuts a week. Co-invest 1-2 MW inside a licensed Lao operator, with a state or bank anchor and a dollar power price; leave the hydro mega-campus for later.

Demand is real but tiny. About 4.5 MW of IT load is in use and the third-party rent pool is near US$7 m a year; rules that keep data in Laos sustain it.

Power is cheap on paper only. The ~4-cent headline sits beside a planned 7.94 cents for industry, plus 2,396 distribution outages in H1 2025.

Report details

Published
2026-10-13
Pages
39
Format
PDF
Code
LA-DCT-ENT-D26-01
Market
Laos
Industry
Data centers & cloud
Year
2026

Table of contents · 10 sections

  1. ES Executive summary
  2. 01 A small market made by rules
  3. 02 Demand grows fast from a tiny base
  4. 03 The cheap-power story is half true
  5. 04 The margin is made in power and anchor contracts
  6. 05 Built alone, a hall takes 19 years to pay back
  7. 06 Room for one neutral operator, not for a 15 GW campus
  8. 07 Decision: enter small, anchored, with power in dollars
  9. 08 Who's who in Lao data centres
  10. Methodology and sources

The full report is available to subscribers and buyers. The executive summary above is free to read.

Key questions

How fast could data-centre demand in Laos grow by 2030?

KIRA estimates Laos data-centre IT load reaches a base case of 12 MW by 2030, within a 6.5 to 40 MW range, according to KIRA's 2026 investment analysis.

Source: Kira estimates, 2030 · KIRA report: Laos data centres 2026: investment analysis

How big is Menas Capital's data-centre MoU in Laos?

Menas Capital signed a non-binding MoU in February 2026 for up to 15 GW of digital infrastructure in Laos, according to KIRA's 2026 investment analysis (Detik Feb 2026).

Source: Detik Feb 2026, 2026 · KIRA report: Laos data centres 2026: investment analysis

How much does an anchor tenant shorten payback for a 2 MW hall in Laos?

With a state or bank anchor pre-letting 90% of capacity, a 2 MW hall in Vientiane pays back in about 8.5 years, according to KIRA's 2026 investment analysis (Kira estimates).

Source: Kira estimates · KIRA report: Laos data centres 2026: investment analysis

What does a data centre cost to build per MW in Laos?

KIRA estimates building a data centre in Laos costs US$7 to 10 m per MW, according to KIRA's 2026 investment analysis (Kira estimates).

Source: Kira estimates · KIRA report: Laos data centres 2026: investment analysis

How long does a stand-alone 2 MW data-centre hall take to pay back in Vientiane?

A stand-alone 2 MW hall in Vientiane pays back in about 19.4 years at base, according to KIRA's 2026 investment analysis (Kira estimates).

Source: Kira estimates · KIRA report: Laos data centres 2026: investment analysis

How many data-centre operators are live in Laos?

Laos has four small live data-centre operators and three studies, leaving room for one neutral, bank-grade operator, according to KIRA's 2026 investment analysis.

Source: KIRA research, 2026 · KIRA report: Laos data centres 2026: investment analysis

What operating margin do data-centre landlords earn?

Data-centre landlords earn about 86.8% operating margin against 49% for global operators, according to KIRA's 2026 investment analysis (Keppel DC FY2025).

Source: Keppel DC FY2025, 2025 · KIRA report: Laos data centres 2026: investment analysis

How big is demand for data centres in Laos today?

About 4.5 MW of data-centre IT load is in use in Laos in 2026, according to KIRA's 2026 investment analysis (Kira estimates).

Source: Kira estimates, 2026 · KIRA report: Laos data centres 2026: investment analysis

How much data-centre capacity is operational in Vietnam?

Vietnam has about 100 MW of data-centre capacity operational, according to KIRA's 2026 investment analysis (VNS 2026).

Source: VNS 2026 · KIRA report: Laos data centres 2026: investment analysis

What is the planned industrial electricity tariff in Laos?

The planned processing-industry power tariff in Laos is 7.94 US cents per kWh in the 2025-29 plan, according to KIRA's 2026 investment analysis (ANN Nov 2025).

Source: ANN Nov 2025 · KIRA report: Laos data centres 2026: investment analysis

How much does delivered power cost per IT kWh in a Vientiane data-centre hall?

A Vientiane data-centre hall pays about 14.1 US cents per kWh of IT load for delivered power, according to KIRA's 2026 investment analysis (Kira estimates).

Source: Kira estimates · KIRA report: Laos data centres 2026: investment analysis

What rent do Laos data-centre halls earn per kW?

KIRA's base case assumes rent of US$200 per kW a month for a Vientiane data-centre hall, according to KIRA's 2026 investment analysis (Kira estimates).

Source: Kira estimates · KIRA report: Laos data centres 2026: investment analysis

Which investment-law incentive applies to data centres in Laos?

Laos's investment law in force since October 2024 grants profit-tax holidays of 4 to 15 years, according to KIRA's 2026 investment analysis.

Source: KIRA research, 2024 · KIRA report: Laos data centres 2026: investment analysis

How many distribution outages hit the Lao grid in the first half of 2025?

The Lao distribution grid logged 2,396 outages and voltage drops in H1 2025, according to KIRA's 2026 investment analysis (VT Aug 2025).

Source: VT Aug 2025, 2025 · KIRA report: Laos data centres 2026: investment analysis

How much power do crypto miners draw in Laos?

Crypto miners draw about 150 MW in Laos, a load the state wants to reassign, according to KIRA's 2026 investment analysis (Reuters Oct 2025).

Source: Reuters Oct 2025, 2025 · KIRA report: Laos data centres 2026: investment analysis