MALAYSIA · CONSTRUCTION · MARKET ANALYSIS

Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

Malaysia's construction market normalises to 6.1% growth in 2026 toward MYR 70.4 bn, but the composition is shifting decisively. Non-residential work grew 18.6% YoY in Q4 2025, led by data-centre shells and SEZ industrial builds. Two structural engines — a ~4 GW Johor data-centre pipeline and MYR 68 bn of JS-SEZ approved investment — anchor demand well beyond the cyclical peak.

Executive summary

Malaysia's construction sector is valued at approximately $28 billion in annual output, entering an expansion phase driven by the Johor-Singapore Special Economic Zone (JS-SEZ) development, data centre construction demand, and resumption of deferred infrastructure projects under the Madani government. The Johor development wave — estimated to require $12–15 billion in construction over 5 years — is the single largest demand driver, encompassing industrial parks, data centres, logistics facilities, and worker accommodation. Industrialised Building System (IBS) and prefabrication adoption, targeted at 50% of public projects by 2025 under the Industrialised Building System Roadmap, is restructuring labour demand and contractor capabilities. Foreign workers — primarily from Bangladesh, Indonesia, and Nepal — represent over 30% of the construction workforce, making labour supply a structural risk. This report covers Malaysia's construction market by segment and region, Johor SEZ construction pipeline, IBS adoption progress, labour market dynamics, major contractor competitive landscape, and the project pipeline outlook through 2026.

Report details

Published
2026-05-31
Pages
23
Format
PDF
Code
MY-CON-XPL-D26-01
Market
Malaysia
Industry
Construction
Year
2026

The full report is available to subscribers and buyers. The executive summary above is free to read.

Key questions

How fast has the construction market in Malaysia grown?

Malaysian construction grew at a 10.5% CAGR over 2021–25 after 11.4% growth in 2025, according to KIRA's 2026 market report (GlobalData 2026).

Source: GlobalData 2026, 2025 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

Which part of the construction market in Malaysia is growing fastest?

Non-residential construction grew 18.6% year on year in Q4 2025, led by industrial and data-centre builds, according to KIRA's 2026 market report (DOSM 2025).

Source: DOSM 2025, 2025 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

How much development spending is planned under Malaysia's 13th Plan?

The 13th Malaysia Plan allocates MYR 430 bn of development expenditure for 2026–30, according to KIRA's 2026 market report (EPU 2025).

Source: EPU 2025, 2026 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

How much have hyperscalers committed to data centres in Malaysia?

KIRA estimates that hyperscaler commitments in Malaysia now exceed USD 12 bn across AWS, Microsoft and Google, according to KIRA's 2026 market report.

Source: Kira estimates, 2026 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

How much investment has the Johor-Singapore Special Economic Zone attracted?

The Johor-Singapore SEZ drew MYR 68 bn of approved investment in the first nine months of 2025, according to KIRA's 2026 market report (MIDA 2025).

Source: MIDA 2025, 2025 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

How concentrated is the construction market in Malaysia?

The top five contractors hold below 33% of Malaysian construction, a fragmented field, according to KIRA's 2026 market report (KIRA estimates).

Source: Kira estimates, 2026 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

Which large construction deals are shaping consolidation in Malaysia?

The proposed Sunway–IJM combination would create a group with about USD 3 bn revenue, overtaking Gamuda, according to KIRA's 2026 market report (Fortune 2026).

Source: Fortune 2026, 2026 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

How much cheaper is industrialised building in Malaysia?

KIRA estimates that prefabrication under the 70% IBS public-project mandate is 15–20% cheaper on labour and about 20% faster, according to KIRA's 2026 market report.

Source: Kira estimates, 2026 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

How big is the construction market in Malaysia?

Construction work done reached MYR 66.3 bn in 2025 and is forecast at MYR 70.4 bn in 2026, according to KIRA's 2026 market report (GlobalData 2026).

Source: GlobalData 2026, 2026 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

Is there a skilled labour shortage in Malaysian construction?

CIDB flags a shortfall of about 180,000 skilled-trade workers in Malaysian construction through 2028, according to KIRA's 2026 market report (CIDB 2025).

Source: CIDB 2025, 2028 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out

How much data-centre power capacity is planned in Johor?

Johor's data-centre pipeline is about 4.0 GW of power capacity, with 700 MW already under construction, according to KIRA's 2026 market report (JLL 2025).

Source: JLL 2025, 2025 · KIRA report: Malaysia construction 2026: data-centre pipeline & Johor-Singapore SEZ build-out