Key questions
How much of Thailand's data-centre demand comes from hyperscalers?
Hyperscalers take at least 80% of Thai data-centre demand, according to KIRA's 2026 market overview (KKPS Oct 2025).
Source: KKPS Oct 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
How long does a grid connection take for a 50 MW data centre in the EEC?
A 50 MW+ grid connection in the EEC takes 18+ months, according to KIRA's 2026 market overview (Mondaq 2026).
Source: Mondaq 2026, 2026 · KIRA report: Thailand data centres 2026: market overview
How fast has the data-centre market in Thailand grown?
Thailand's data-centre and cloud services market grew 24% a year since 2019, from THB 20 bn in 2019, according to KIRA's 2026 market overview (Colliers 2025).
Source: Colliers 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
What are the largest announced data-centre projects in Thailand?
Zenith DC & Cloud and Bridge QHI01 each have 200 MW of announced capacity, the largest projects in Thailand, according to KIRA's 2026 market overview (BOI Nov 2025).
Source: BOI Nov 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
Which Thai province attracts the most data-centre investment applications?
Rayong took 33% of 2025 data-centre BOI application value, ahead of Chonburi at 32%, according to KIRA's 2026 market overview (BOI 2025).
Source: BOI 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
How large is the Japanese-led data-centre project in Thailand?
Telehouse (KDDI) is the largest Japanese-led data-centre approval in Thailand at 12 MW, according to KIRA's 2026 market overview (BOI Nov 2025).
Source: BOI Nov 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
How much data-centre investment did Thailand's BOI receive in 2025?
Data-centre investment applications to Thailand's BOI reached THB 728 bn across 36 projects in 2025, according to KIRA's 2026 market overview (BOI 2025).
Source: BOI 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
Which operator has the most data-centre sites in Thailand?
National Telecom (NT) has 13 data-centre sites, ahead of AIS with 8 and True IDC with 4, out of 60 sites as of Mar 2026, according to KIRA's 2026 market overview (LH Bank 2026).
Source: LH Bank 2026, 2026 · KIRA report: Thailand data centres 2026: market overview
How much of data-centre operating cost is energy?
Energy is about 70% of data-centre operating cost in Thailand, according to KIRA's 2026 market overview (Nation Aug 2026).
Source: Nation Aug 2026, 2026 · KIRA report: Thailand data centres 2026: market overview
How much data-centre capacity is live in Thailand for tenants to rent?
About 216 MW of colocation capacity is live in Thailand as of Q2 2026, according to KIRA's 2026 market overview (BMI Jun 2026).
Source: BMI Jun 2026, 2026 · KIRA report: Thailand data centres 2026: market overview
How much data-centre capacity is under construction or planned in Thailand?
Under construction and planned data-centre capacity in Thailand totals 944 MW as of Q2 2026, according to KIRA's 2026 market overview (Mondaq 2026).
Source: Mondaq 2026, 2026 · KIRA report: Thailand data centres 2026: market overview
How much of Thailand's live data-centre capacity is in Bangkok?
Bangkok metro holds 145.8 MW of the 216 MW of live colocation (67%), with Chonburi at 70 MW (33%), according to KIRA's 2026 market overview (BMI Jun 2026).
Source: BMI Jun 2026, 2026 · KIRA report: Thailand data centres 2026: market overview
How big is the data-centre market in Thailand?
Thailand's data-centre and cloud services market reached THB 73 bn in 2025, according to KIRA's 2026 market overview (Colliers 2025).
Source: Colliers 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
How much is spent on cloud within Thailand's data-centre and cloud market?
Public cloud spend in Thailand is about THB 67 bn in 2025, the bulk of data-centre and cloud services, according to KIRA's 2026 market overview (AWS TH 2025).
Source: AWS TH 2025, 2025 · KIRA report: Thailand data centres 2026: market overview
What electricity tariff is proposed for data centres in Thailand?
A Category 9 tariff of THB 5-6 per kWh is proposed for data centres in Thailand, according to KIRA's 2026 market overview (MoE Tariff 2026).
Source: MoE Tariff 2026, 2026 · KIRA report: Thailand data centres 2026: market overview
More on Data centres in Thailand