MALAYSIA · DATA CENTERS & CLOUD · MARKET SCAN

Malaysia data centres 2026: market overview

Is data centre supply racing ahead of demand, or still catching up?

Executive summary

The tension: Johor halls are 99% let, yet signed grid supply is about nine times the capacity that is live. Back capacity that has grid power, an air-cooled or reclaimed-water design and an anchor tenant; treat everything else in the pipeline as an option, not supply.

Live supply is catching up. Pre-leased capacity reached 1.2 GW in 1H2026, above the 926 MW BMI counts live; Johor colocation vacancy is 0.7%.

The paper pipeline is racing ahead. TNB has signed 8.35 GW of supply agreements; we expect about 5 GW of IT capacity live by 2030 in our base case.

Report details

Published
2026-11-16
Pages
37
Format
PDF
Code
MY-DCT-XPL-D26-05
Market
Malaysia
Industry
Data centers & cloud
Year
2026

Table of contents · 8 sections

  1. ES Executive summary
  2. 01 A market that has doubled in two years
  3. 02 Wholesale campuses in Johor hold most of the market
  4. 03 Water and grid, not demand, set the pace
  5. 04 Three groups built the first wave; a dozen are building the next
  6. 05 Where a foreign company can win
  7. 06 Who's who in Malaysian data centres
  8. 07 Methodology and sources

The full report is available to subscribers and buyers. The executive summary above is free to read.

Key questions

Which customer groups take the most leased data centre space in Malaysia?

KIRA estimates US hyperscale clouds take 45% of leased data centre MW in Malaysia, ahead of Chinese cloud and internet at 25%, according to KIRA's 2026 market overview.

Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview

What entry routes into Malaysian data centres have precedents?

Five routes have precedents: an own greenfield campus, a JV with a landholder, buying an operating site, a capital partner in a developer, and supply and build for cooling and power gear, according to KIRA's 2026 market overview (NTT 2026; Techwire Jun 2026).

Source: NTT 2026; DCD Mitsui; Techwire Jun 2026; AirTrunk Apr 2026; Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview

Which data centre segments are most open to a foreign company in Malaysia?

KIRA scores cooling and power gear highest on ability to win at 8.5 out of 10, against 3.5 for Johor wholesale campuses, according to KIRA's 2026 market overview (Kira estimates).

Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview

How big could Malaysia's data centre capacity be by 2030?

KIRA's 2030 base case is 5.0 GW of live IT load, within a 3.5-7.0 GW scenario range, from 1.0 GW at end-2025, according to KIRA's 2026 market overview (JLL 2Q2026; Kira estimates).

Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: market overview

How fast is data centre capacity in Malaysia growing?

Operational capacity was 1,025 MW at end-2025, up from 522 MW in Q1 2025, and consultants forecast 2,055 MW by end-2026, according to KIRA's 2026 market overview (Juwai IQI Sep 2026; JLL 2Q2026).

Source: Juwai IQI Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview

How much have cloud providers pledged to invest in Malaysia?

Cloud providers have pledged US$32 bn of investment in Malaysia, including Google's US$15 bn for 2027-2028, according to KIRA's 2026 market overview (Google Nov 2026). Pledges are announced, not spent.

Source: Google Nov 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview

How much data centre investment has Malaysia approved?

Approved data centre investment totalled RM144 bn for 143 projects from 2021 to October 2025, and 27 task-force projects are worth RM225.97 bn; these are approvals, not money spent, according to KIRA's 2026 market overview (BT Nov 2025; Star Oct 2026).

Source: BT Nov 2025, 2025 · KIRA report: Malaysia data centres 2026: market overview

Which Japanese companies are active in Malaysian data centres?

NTT DATA runs a 290 MW campus at Gelang Patah, two Japanese projects hold RM1.79 bn of data centre approvals, and KIRA found no announced Korean developer or operator project, according to KIRA's 2026 market overview (NTT 2026; MITI Jul 2026).

Source: NTT 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview

Which developers have the largest announced data centre campuses in Malaysia?

YTL's planned Kulai park, at 1,200 MW, is the largest announced campus, ahead of AirTrunk's four campuses at 700 MW; these are full-build figures, not live capacity, according to KIRA's 2026 market overview.

Source: Edge Oct 2026; AirTrunk Apr 2026; RTM 2026; Telecomtalk 2025; NTT 2026; Utusan Dec 2025; PDG 2026; Techwire Jun 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview

Who are the biggest data centre operators in Malaysia?

Bridge, DayOne and YTL held about 69% of built IT capacity in December 2024, excluding cloud-owned halls, with Bridge at 32% and DayOne at 29%, according to KIRA's 2026 market overview (TechNode Jan 2025).

Source: TechNode Jan 2025, 2024 · KIRA report: Malaysia data centres 2026: market overview

What share of Malaysia's live data centre capacity is wholesale hyperscale?

KIRA estimates wholesale hyperscale campuses hold 65% of Malaysia's live IT capacity in mid-2026, the largest share of any facility type, according to KIRA's 2026 market overview.

Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview

How do Malaysia's data centre clusters compare on live capacity and vacancy?

Johor has 1,110 MW of live IT capacity and 0.7% vacancy, with new Tier 1-2 approvals stopped, while Greater KL has about 600 MW building, according to KIRA's 2026 market overview (Knight Frank 2026; C&W H1 2026).

Source: Knight Frank 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview

Is data centre supply in Malaysia catching up with demand or racing ahead?

Supply is still catching up: pre-leased capacity reached 1.2 GW in 1H2026, above the 926 MW counted live in October 2026, according to KIRA's 2026 market overview (Juwai IQI Sep 2026; BMI Oct 2026).

Source: Juwai IQI Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview

How much data centre capacity is under construction or planned in Malaysia?

Malaysia had 2,000 MW under construction and 3,100 MW planned in 2026, on top of 926 MW live, according to KIRA's 2026 market overview (BMI Oct 2026; HLIB Jun 2026).

Source: BMI Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview

How much data centre capacity is live in Malaysia in 2026?

KIRA puts national live IT capacity at 1.3-1.5 GW in mid-2026, about 1.4 GW, while BMI counts 926 MW live in October 2026, according to KIRA's 2026 market overview (BMI Oct 2026; Kira estimates).

Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview

More on Data centres in Malaysia