Malaysia Data centres: key facts
Market size
Which AI process area in Malaysian data centres has the largest value pool?
Cooling and energy control has the largest AI value pool in Malaysian data centres at RM0.2-0.8 bn a year at 2030 adoption, according to KIRA's 2026 AI impact and use cases analysis (Kira estimates).
Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much value can AI add inside Malaysian data centre operations?
AI inside data-centre operations is worth RM0.7-2.6 bn a year by 2030, of which cooling and energy RM0.2-0.8 bn, according to KIRA's 2026 AI impact and use cases analysis (Kira estimates).
Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much power will data centres in Johor need by 2030?
Johor's projected 2030 data-centre peak demand is 4428 MW, the largest of any state, according to KIRA's 2026 regulatory landscape analysis (PETRA via Bernama 2026).
Source: PETRA via Bernama 2026, 2030 · KIRA report: Malaysia data centres 2026: regulatory landscape
How much water has Malaysia approved for data centres?
Malaysia has approved 445.04 MLD of water for data centres to 2030, of which 63.9 MLD was in use in June 2026, according to KIRA's 2026 regulatory landscape analysis (The Star Oct 2026).
Source: The Star Oct 2026, 2030 · KIRA report: Malaysia data centres 2026: regulatory landscape
How much of the planned data-centre power pipeline in Peninsular Malaysia is still in planning?
79 data-centre projects in Peninsular Malaysia are in planning, with 25.6 GW of maximum demand, according to KIRA's 2026 AI impact and use cases analysis (TNB May 2026; RHB Jul 2026).
Source: TNB May 2026, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much is being spent building new data-centre halls in Malaysia?
Build spend on new data-centre halls in Malaysia is RM22.0-36.0 bn in 2026, according to KIRA's 2026 AI impact and use cases analysis (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much operational data-centre IT capacity does Malaysia have?
Malaysia's operational data-centre IT capacity was 522 MW in Q1 2025 and should reach 2,055 MW by end-2026, according to KIRA's 2026 trends and outlook analysis (Juwai Sep 2026).
Source: Juwai Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How full is the Johor data-centre market?
Johor colocation vacancy is 0.7%, so its data-centre halls are close to full, according to KIRA's 2026 trends and outlook analysis (KF Atlas 2026).
Source: KF Atlas 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much is spent each year building data centres in Malaysia?
Construction and fit-out capex is the largest data-centre spend pool in Malaysia at USD 5-10 bn a year in 2026, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much of Malaysia's approved data-centre power is actually drawn?
Data centres drew 1.37 GW in August 2026, about 11% of the capacity already approved, according to KIRA's 2026 regulatory landscape analysis (The Star Oct 2026; PETRA via Bernama 2026).
Source: The Star Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
How many flagship data-centre projects has Johor approved?
The task force has approved 16 flagship data-centre projects in Johor and 10 in Selangor, cumulative to July 2026, according to KIRA's 2026 trends and outlook analysis (DCTF Sep 2026).
Source: DCTF Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How many approved data-centre projects in Malaysia are not yet operating?
62 of 117 approved data-centre projects in Malaysia are not yet operating, so capacity is rationed rather than scarce, according to KIRA's 2026 regulatory landscape analysis (W.Media Oct 2026).
Source: W.Media Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
How much data-centre power has Malaysia approved?
Malaysia has approved 12.3 GW of data-centre grid capacity as of August 2026, against a projected 8.39 GW peak in 2030, according to KIRA's 2026 regulatory landscape analysis (The Star Oct 2026).
Source: The Star Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
How much data-centre capacity is live in Johor?
Johor had 1,110 MW of operational data-centre IT load in the first half of 2026, according to KIRA's 2026 trends and outlook analysis (C&W H1 2026).
Source: C&W H1 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much data centre capacity is live in Johor?
Johor has about 850 MW of live data centre capacity, about 700 MW building and about 3,300 MW in the pipeline, according to KIRA's 2026 market report (KIRA estimates).
Source: Kira estimates, 2026 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
How much data centre capacity does Malaysia have in 2026?
Malaysia's data centre capacity is about 2,055 MW in 2026, roughly 2x 2024 levels, according to KIRA's 2026 market report (JLL 2026).
Source: JLL 2026, 2026 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
Is data centre supply in Malaysia catching up with demand or racing ahead?
Supply is still catching up: pre-leased capacity reached 1.2 GW in 1H2026, above the 926 MW counted live in October 2026, according to KIRA's 2026 market overview (Juwai IQI Sep 2026; BMI Oct 2026).
Source: Juwai IQI Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
How much data centre capacity is live in Malaysia in 2026?
KIRA puts national live IT capacity at 1.3-1.5 GW in mid-2026, about 1.4 GW, while BMI counts 926 MW live in October 2026, according to KIRA's 2026 market overview (BMI Oct 2026; Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview
How much data centre capacity is under construction or planned in Malaysia?
Malaysia had 2,000 MW under construction and 3,100 MW planned in 2026, on top of 926 MW live, according to KIRA's 2026 market overview (BMI Oct 2026; HLIB Jun 2026).
Source: BMI Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
How do Malaysia's data centre clusters compare on live capacity and vacancy?
Johor has 1,110 MW of live IT capacity and 0.7% vacancy, with new Tier 1-2 approvals stopped, while Greater KL has about 600 MW building, according to KIRA's 2026 market overview (Knight Frank 2026; C&W H1 2026).
Source: Knight Frank 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
What share of Malaysia's live data centre capacity is wholesale hyperscale?
KIRA estimates wholesale hyperscale campuses hold 65% of Malaysia's live IT capacity in mid-2026, the largest share of any facility type, according to KIRA's 2026 market overview.
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview
How much live data-centre IT load is there in Malaysia?
Malaysia had about 1.5 GW of live data-centre IT load in 2025, up from about 10 MW in 2022, according to KIRA's 2026 market report (Introl 2025).
Source: Introl 2025, 2025 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
How big is Malaysia's data-centre market?
Malaysia's data-centre market was about USD 6.1 bn in 2025, according to KIRA's 2026 market report (DC Market 2026).
Source: DC Market 2026, 2025 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
How much power do Malaysian data centres declare compared with what they use?
Malaysian data centres declared 1276 MW of maximum demand in June 2025 but actually used 603 MW, according to KIRA's 2026 AI impact and use cases analysis (EC Jun 2025).
Source: EC Jun 2025, 2025 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How big is data centre colocation and lease revenue in Malaysia?
KIRA estimates lease revenue at US$0.9-1.3 bn in 2025, between an APDCA study at US$0.71 bn and an Arizton estimate of US$1.34 bn, according to KIRA's 2026 market overview (APDCA 2025; Arizton 2026; Kira estimates).
Source: Kira estimates, 2025 · KIRA report: Malaysia data centres 2026: market overview
How much electricity do data centres actually draw from the grid in Malaysia?
Actual data centre load in Peninsular Malaysia was 850 MW at end-2025, against 8.35 GW of signed supply agreements, according to KIRA's 2026 market overview (HLIB Jun 2026; Malay Mail Jul 2026; ADL Oct 2026).
Source: HLIB Jun 2026; Malay Mail Jul 2026; ADL Oct 2026, 2025 · KIRA report: Malaysia data centres 2026: market overview
Growth
How fast is Malaysia's data-centre market growing?
Malaysia's data-centre market is forecast to grow about 20% a year to 2031, according to KIRA's 2026 market report (DC Market 2026).
Source: DC Market 2026, 2031 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
How much data-centre capacity will Malaysia have by 2030?
On today's path Malaysia reaches 4.5-5.5 GW of data-centre IT capacity by 2030, with 3.0-8.5 GW across four scenarios, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: trends and outlook
What is the 2030 data-centre capacity in the full-build scenario for Malaysia?
In KIRA's full-build scenario, Malaysia reaches 6.5-8.5 GW of operational IT capacity by 2030, against a power-queue scenario of 3.8-4.8 GW (Kira estimates scenario).
Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: trends and outlook
How big is the data centre market in Malaysia, and how fast is it growing?
Malaysia's data centre market value is forecast at USD 13.6 bn by 2030, growing at a 22.4% CAGR, according to KIRA's 2026 market report (Arizton 2025).
Source: Arizton 2025, 2030 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
How big could Malaysia's data centre capacity be by 2030?
KIRA's 2030 base case is 5.0 GW of live IT load, within a 3.5-7.0 GW scenario range, from 1.0 GW at end-2025, according to KIRA's 2026 market overview (JLL 2Q2026; Kira estimates).
Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: market overview
How fast is data centre capacity in Malaysia growing?
Operational capacity was 1,025 MW at end-2025, up from 522 MW in Q1 2025, and consultants forecast 2,055 MW by end-2026, according to KIRA's 2026 market overview (Juwai IQI Sep 2026; JLL 2Q2026).
Source: Juwai IQI Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
How fast did live data centre supply in Johor grow before 2025?
Live Johor data centre supply grew ~145% a year over 2019-2024, according to KIRA's 2026 market report (Arizton 2025).
Source: Arizton 2025, 2024 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
Trends
Which AI use cases in Malaysian data centres have no local case yet?
Security video analytics, control-system cyber watch, energy trading, water analytics and tenant service desks have no Malaysian case found, according to KIRA's 2026 AI impact and use cases analysis.
Source: KIRA research, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much power does a GPU cluster rack need in Malaysia?
AI GPU racks in Malaysia need 70-107 kW each, against 5-10 kW in earlier halls, according to KIRA's 2026 trends and outlook analysis (Edge Sep 2026).
Source: Edge Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
Is Malaysia building AI-ready data centre capacity, and how big is the first live cluster?
A live 600 MW accelerated cluster in Kulai signals Malaysia's shift to GPU-dense AI campuses, according to KIRA's 2026 market report (Converge 2026).
Source: Converge 2026, 2026 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
How much power does a liquid-cooled AI rack need?
A liquid-cooled GB200 NVL72 rack draws about 120 kW, against 40 kW for an air-cooled H100 rack, according to KIRA's 2026 AI impact and use cases analysis (SemiAnalysis 2024).
Source: SemiAnalysis 2024, 2024 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much cooling energy did Google report saving with AI control?
Google reported a 40% saving in cooling energy from AI control at one site in 2016, according to KIRA's 2026 AI impact and use cases analysis (Google 2016).
Source: Google 2016, 2016 · KIRA report: Malaysia data centres 2026: AI impact and use cases
Key players
How much data-centre construction work has Gamuda won in Malaysia in 2026?
Gamuda holds RM7.0 bn of data-centre jobs in Malaysia in 2026, according to KIRA's 2026 AI impact and use cases analysis (Gamuda 2026).
Source: Gamuda 2026, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
Which developers have the largest announced data centre campuses in Malaysia?
YTL's planned Kulai park, at 1,200 MW, is the largest announced campus, ahead of AirTrunk's four campuses at 700 MW; these are full-build figures, not live capacity, according to KIRA's 2026 market overview.
Source: Edge Oct 2026; AirTrunk Apr 2026; RTM 2026; Telecomtalk 2025; NTT 2026; Utusan Dec 2025; PDG 2026; Techwire Jun 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
Which Japanese companies are active in Malaysian data centres?
NTT DATA runs a 290 MW campus at Gelang Patah, two Japanese projects hold RM1.79 bn of data centre approvals, and KIRA found no announced Korean developer or operator project, according to KIRA's 2026 market overview (NTT 2026; MITI Jul 2026).
Source: NTT 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
Which Johor AI-ready data-centre campus has the largest announced capacity?
YTL's Kulai AI campus in Johor leads announced AI-ready capacity at 300 MW, ahead of NTT DATA Gelang Patah at 290 MW, according to KIRA's 2026 AI impact and use cases analysis (YTL Nov 2025).
Source: YTL Nov 2025, 2025 · KIRA report: Malaysia data centres 2026: AI impact and use cases
Who are the biggest data centre operators in Malaysia?
Bridge, DayOne and YTL held about 69% of built IT capacity in December 2024, excluding cloud-owned halls, with Bridge at 32% and DayOne at 29%, according to KIRA's 2026 market overview (TechNode Jan 2025).
Source: TechNode Jan 2025, 2024 · KIRA report: Malaysia data centres 2026: market overview
Pricing
What service tax applies to data-centre rentals in Malaysia?
Rental of space and servers is subject to service tax at 6% from 1 January 2026, down from 8% in July to December 2025, according to KIRA's 2026 regulatory landscape analysis (PwC MTB 2026).
Source: PwC MTB 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
What electricity price does a data centre face in Malaysia?
The ultra-high voltage tariff averages about 60 sen per kWh for a data centre, and 58-70 sen at a low load factor, according to KIRA's 2026 regulatory landscape analysis (analyst estimates; Malay Mail Sep 2026).
Source: Malay Mail Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
How much did Peninsular Malaysia's base electricity tariff rise for data centres?
The Peninsular base tariff rose from 39.96 to 45.62 sen/kWh for RP4 (July 2025 to December 2026), according to KIRA's 2026 market report (TNB 2025).
Source: TNB 2025, 2026 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
What do data centres pay for electricity in Malaysia?
Data centres pay about 60 sen per kWh under the July 2025 RP4 tariff, against a 45.62 sen base, according to KIRA's 2026 AI impact and use cases analysis (w.media Jul 2025).
Source: w.media Jul 2025, 2025 · KIRA report: Malaysia data centres 2026: AI impact and use cases
What does Johor charge for water to data centres?
Johor set a data-centre water tariff of RM5.33 per cubic metre in August 2025, according to KIRA's 2026 trends and outlook analysis (Bernama Aug 2025).
Source: Bernama Aug 2025, 2025 · KIRA report: Malaysia data centres 2026: trends and outlook
What electricity price does a data centre pay in Malaysia?
A data centre pays about 60 sen per kWh on the ultra-high voltage tariff, against a 45.62 sen RP4 base tariff from July 2025, according to KIRA's 2026 trends and outlook analysis (TNB RP4 2024).
Source: TNB RP4 2024, 2025 · KIRA report: Malaysia data centres 2026: trends and outlook
How much do data centres pay for water in Johor?
Johor set the data centre water tariff at RM5.33 per m3 in August 2025, and up to 12 MLD of reclaimed water is allowed for cooling, according to KIRA's 2026 market overview (Star Aug 2025).
Source: Star Aug 2025, 2025 · KIRA report: Malaysia data centres 2026: market overview
How much has the electricity tariff for large users in Peninsular Malaysia changed?
The base tariff rose from 39.95 sen per kWh to 45.40 sen from July 2025, and analysts put the new ultra-high-voltage band around 60 sen, according to KIRA's 2026 market overview (ST RP4 2025).
Source: ST RP4 2025, 2025 · KIRA report: Malaysia data centres 2026: market overview
Why is Singapore overflow pulling data centre demand into Malaysia?
Singapore rents data centre space at US$330-475 per kW a month and Malaysian costs are about 30% lower, a strong pull that KIRA rates steady to 2028, according to KIRA's 2026 market overview (JPM via Mingtiandi; Focus Malaysia 2026).
Source: JPM via Mingtiandi · KIRA report: Malaysia data centres 2026: market overview
Margins
How much annual saving can AI cooling control bring to a 100 MW hall in Malaysia?
KIRA estimates AI cooling control saves RM10.3-25.8 mn a year in an older 100 MW hall at PUE 1.4, according to KIRA's 2026 AI impact and use cases analysis (Kira estimates; tariff w.media Jul 2025).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much rent do data-centre operators earn in Malaysia?
Leasing rent is the steadiest data-centre spend pool in Malaysia at USD 1.3-1.8 bn a year in 2026, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
Customers and demand
What is the national average monthly pay for a technician in Malaysian data centres?
The national average monthly pay for a data-centre technician in Malaysia is RM3768, according to KIRA's 2026 AI impact and use cases analysis (NST Jul 2026; Indeed 2026).
Source: NST Jul 2026, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much do senior roles earn in Malaysian data centres?
Senior roles in Malaysian data centres pay RM10,000-30,000 a month, according to KIRA's 2026 AI impact and use cases analysis (NST Jul 2026; Indeed 2026).
Source: NST Jul 2026, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
Which customer groups take the most leased data centre space in Malaysia?
KIRA estimates US hyperscale clouds take 45% of leased data centre MW in Malaysia, ahead of Chinese cloud and internet at 25%, according to KIRA's 2026 market overview.
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview
Trade flows
How much data-centre capacity is under construction in Malaysia compared with Thailand?
Malaysia had 1,039 MW of data-centre IT capacity under construction in H1 2026, against 859 MW in Thailand, according to KIRA's 2026 trends and outlook analysis (C&W H1 2026).
Source: C&W H1 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How many AI chips is a Chinese tenant running in Malaysia?
ByteDance plans to use 36,000 B200 chips in Malaysia from March 2026, according to KIRA's 2026 trends and outlook analysis (w.media Mar 2026).
Source: w.media Mar 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
Regulation
When is Malaysia's AI law expected to be tabled?
Malaysia's risk-based AI Governance Bill is due for tabling in early 2027, with tiered duties for AI deployers, according to KIRA's 2026 AI impact and use cases analysis.
Source: NAIO Jul 2026, 2027 · KIRA report: Malaysia data centres 2026: AI impact and use cases
When is Johor's water-cooling pause expected to lift?
Johor's water-cooling pause is expected to lift in mid-2027, and only with reclaimed water, according to KIRA's 2026 regulatory landscape analysis (Johor state committee statement).
Source: KIRA research, 2027 · KIRA report: Malaysia data centres 2026: regulatory landscape
When is Johor's water-cooling pause expected to lift?
Johor's water-cooling pause, set after Johor stopped Tier 1-2 approvals in November 2025, is expected to lift in mid-2027, according to KIRA's 2026 trends and outlook analysis (MITI Guidelines 2025).
Source: KIRA research, 2027 · KIRA report: Malaysia data centres 2026: trends and outlook
What water-use efficiency does Johor look for in a data centre?
Johor's guidance recommends about 1.8 litres per kW of water use efficiency, and the sustainable data-centre guidelines set design WUE at 2.2 for incentives, according to KIRA's 2026 AI impact and use cases analysis (Malay Mail Jan 2026).
Source: Malay Mail Jan 2026, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How many data-centre applications did Johor's task force assess?
Johor's MIDA task force judged over 40 data-centre applications in 2026 on energy, water and links, with 30% local content, according to KIRA's 2026 AI impact and use cases analysis.
Source: KIRA research, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
What renewable-energy share will data centres in Malaysia need?
The green-power rule requires at least 30% renewable energy on total demand capacity for data centres, but the framework is still being drafted, according to KIRA's 2026 regulatory landscape analysis (Energy Commission).
Source: KIRA research, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
What local-content share must a data-centre approval meet?
A data-centre approval must reach at least 30% local domestic content, reported every six months to the task force and MIDA, according to KIRA's 2026 regulatory landscape analysis (Bernama Sep 2026).
Source: Bernama Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
How many approval gates must a data-centre project in Malaysia pass?
A data-centre project in Malaysia must pass five gates, held by at least six bodies federal and state, according to KIRA's 2026 regulatory landscape analysis (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
How much grid power has TNB signed for data centres in Malaysia?
TNB has signed 8.35 GW of data centre supply agreements, which is contracted grid power rather than load, according to KIRA's 2026 market overview (HLIB Jun 2026).
Source: HLIB Jun 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
Which Malaysian states have approved the most data centre projects?
Johor has 16 of the 27 projects approved by the Data Centre Task Force up to July 2026, ahead of Selangor with 10 and Negeri Sembilan with 1, according to KIRA's 2026 market overview (Star Oct 2026).
Source: Star Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
What are the penalties under Malaysia's data-protection amendments?
Malaysia's 2025 data-protection amendments set fines of up to RM1 mn for breaches and add processor duties, according to KIRA's 2026 AI impact and use cases analysis (PDPA 2024).
Source: PDPA 2024, 2025 · KIRA report: Malaysia data centres 2026: AI impact and use cases
What corporate tax rate does the Johor-Singapore SEZ offer?
The Johor-Singapore SEZ offers 5% corporate tax for up to 15 years to named sectors since January 2025, and data centres are not named, according to KIRA's 2026 regulatory landscape analysis (MOF Jan 2025).
Source: MOF Jan 2025, 2025 · KIRA report: Malaysia data centres 2026: regulatory landscape
What tax incentive does the Johor-Singapore SEZ offer data centre investors?
The January 2025 JS-SEZ pact offers a 5% corporate tax rate for up to 15 years plus a 100% investment tax allowance, with applications to MIDA through 31 Dec 2034, according to KIRA's 2026 market report (MIDA 2025).
Source: MIDA 2025, 2025 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
Market entry
Which Malaysian location has the best site screen for a new data-centre campus?
Johor (Sedenak, Kulai, Iskandar Puteri) scores highest in KIRA's site screen at 3.4 out of 5, ahead of Selangor Cyberjaya at 3.2, according to KIRA's 2026 regulatory landscape analysis (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape
Which data centre segments are most open to a foreign company in Malaysia?
KIRA scores cooling and power gear highest on ability to win at 8.5 out of 10, against 3.5 for Johor wholesale campuses, according to KIRA's 2026 market overview (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview
What entry routes into Malaysian data centres have precedents?
Five routes have precedents: an own greenfield campus, a JV with a landholder, buying an operating site, a capital partner in a developer, and supply and build for cooling and power gear, according to KIRA's 2026 market overview (NTT 2026; Techwire Jun 2026).
Source: NTT 2026; DCD Mitsui; Techwire Jun 2026; AirTrunk Apr 2026; Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview
How big is Johor's upcoming data centre pipeline?
Johor's upcoming data centre pipeline is about 4.0 GW, with 700 MW under construction, according to KIRA's 2026 market report (DCD 2025).
Source: DCD 2025, 2025 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
Can a foreign company fully own a data centre in Malaysia?
A foreign company can hold 100% of a colocation or wholesale data centre through a wholly owned local company, according to KIRA's 2026 regulatory landscape analysis (Skrine 2024).
Source: Skrine 2024, 2024 · KIRA report: Malaysia data centres 2026: regulatory landscape
What is the foreign equity cap for a network facility in Malaysia?
Foreign equity in an individual NFP or NSP network licence is capped at up to 49%, with at least 30% bumiputera ownership, according to KIRA's 2026 regulatory landscape analysis (Skrine 2024; MCMC ASP(C) 2022).
Source: Skrine 2024, 2024 · KIRA report: Malaysia data centres 2026: regulatory landscape
Investment
How much has AWS planned to invest in Malaysia?
AWS plans more than USD 6.2 bn of investment in Malaysia through 2038, according to KIRA's 2026 market report (AWS 2024).
Source: AWS 2024, 2038 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
How large is the tax allowance for digital infrastructure investment in Malaysia?
The DESAC scheme gives a 100% investment tax allowance on qualifying capex, up to 100% of statutory income for up to 10 years, with applications open to 31 Dec 2027, according to KIRA's 2026 regulatory landscape analysis (MIDA DESAC 2024).
Source: MIDA DESAC 2024, 2027 · KIRA report: Malaysia data centres 2026: regulatory landscape
What is the Johor AirTrunk campus worth in a possible sale?
AirTrunk's Johor campus is in sale talks at about US$1 bn, according to KIRA's 2026 AI impact and use cases analysis.
Source: KIRA research, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How much of Malaysia's approved investment in H1 2026 went to data centres?
Data centres and cloud took RM95.8 bn of the RM218.5 bn approved investment in Malaysia in January to June 2026, according to KIRA's 2026 trends and outlook analysis (MIDA H1 2026).
Source: MIDA H1 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much have cloud providers pledged to invest in Malaysia?
Cloud providers have pledged US$32 bn of investment in Malaysia, including Google's US$15 bn for 2027-2028, according to KIRA's 2026 market overview (Google Nov 2026). Pledges are announced, not spent.
Source: Google Nov 2026, 2026 · KIRA report: Malaysia data centres 2026: market overview
How much investment did Malaysia approve in 2025?
Malaysia's approved investment reached MYR 427 b in 2025, up 11.0% and a record high, according to KIRA's 2026 market report (MIDA 2026).
Source: MIDA 2026, 2025 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
How much of Johor's approved investment goes to JS-SEZ projects?
JS-SEZ projects were 74.6% of Johor's RM91.1 bn approved investment in January-September 2025, according to KIRA's 2026 market report (MIDA 2025).
Source: MIDA 2025, 2025 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
How much data centre investment has Malaysia approved?
Approved data centre investment totalled RM144 bn for 143 projects from 2021 to October 2025, and 27 task-force projects are worth RM225.97 bn; these are approvals, not money spent, according to KIRA's 2026 market overview (BT Nov 2025; Star Oct 2026).
Source: BT Nov 2025, 2025 · KIRA report: Malaysia data centres 2026: market overview
How much has Google committed to Malaysia cloud?
Google committed USD 2 b to Malaysia, according to KIRA's 2026 market report (Google 2024).
Source: Google 2024, 2024 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
How much have hyperscalers announced for cloud investment in Malaysia?
Oracle announced USD 6.5 bn of cloud investment in Malaysia, with AWS at USD 6.2 bn, according to KIRA's 2026 trends and outlook analysis (Oracle Oct 2024).
Source: Oracle Oct 2024, 2024 · KIRA report: Malaysia data centres 2026: trends and outlook
How much cloud and AI capital has been announced in Malaysia?
About USD 20.3 bn of cloud and AI capital has been announced in Malaysia, according to KIRA's 2026 market report (MI 2026).
Source: MI 2026 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
Risks
How much cooling energy can AI cooling control save?
KIRA estimates AI cooling control saves 10-25% of cooling energy in a Malaysian hall, with no published Malaysian result found, according to KIRA's 2026 AI impact and use cases analysis.
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: AI impact and use cases
How long does a grid connection take for a data centre in Malaysia?
A grid connection takes 24-96 months from decision to service for a data centre in Malaysia, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: KIRA research, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
What must a foreign company have in place to win in Malaysian data centres?
KIRA lists six conditions to win, including 30% local content with Malaysian builders (high confidence) and a site with a signed TNB supply agreement (medium confidence), according to KIRA's 2026 market overview (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: market overview
How large is the power connection queue for data centres in Malaysia?
The grid connection queue for data centres in Malaysia exceeds 11,000 MW of applications, according to KIRA's 2026 market report (TNB 2025).
Source: TNB 2025, 2025 · KIRA report: Johor's data centre build-out at the JS-SEZ inflection
What could slow data centre growth in Johor?
Johor stopped approving new Tier 1 and Tier 2 data centres in November 2025, and water-cooled expansions were told to wait until about mid-2027, according to KIRA's 2026 market overview (Star Nov 2025; SCMP 2025).
Source: Star Nov 2025, 2025 · KIRA report: Malaysia data centres 2026: market overview
What share of new data-centre applications did Johor reject in 2024?
Johor rejected roughly 30% of new data-centre applications in 2024 on utility-timeline and water grounds, according to KIRA's 2026 market report (DCD 2025).
Source: DCD 2025, 2024 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
How long does a grid connection take under TNB's Green Lane?
TNB's Green Lane compresses grid connection for data centres to about 12 months, according to KIRA's 2026 market report (TNB 2024).
Source: TNB 2024, 2024 · KIRA report: Malaysia cloud infrastructure — hyperscaler landings and sovereign-cloud demand
Other questions
How much grid power would Malaysia's data centres need in 2030?
KIRA's base case needs 7.0 GW of grid power in 2030 (5 GW of IT load at PUE 1.4), against an official 2030 data centre demand of 12.9 GW, according to KIRA's 2026 market overview (HLIB Jun 2026; EOR 2027; Kira estimates).
Source: HLIB Jun 2026; EOR 2027; Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: market overview