MALAYSIA · DATA CENTERS & CLOUD · MARKET SCAN

Malaysia data centres 2026: regulatory landscape

Which rules on power, water and location now decide where a data centre can rise?

Executive summary

There is no moratorium. Since late 2025 the state has moved from attracting capacity to rationing it: by water, by grid headroom and by a 30% renewable rule. Our answer for a foreign entrant: conditional go. Build where power and water are already committed, and price every rule before buying land.

12.3 GW: Grid capacity approved for data centres, Aug 2026. Against a projected 8.4 GW peak in 2030 and 1.4 GW actually drawn. The government now screens every project on water, power, green supply and the investor's balance sheet.

Report details

Published
2026-11-07
Pages
35
Format
PDF
Code
MY-DCT-XPL-D26-04
Market
Malaysia
Industry
Data centers & cloud
Year
2026

Table of contents · 9 sections

  1. 04 Executive summary
  2. 05 Laws, licences and regulators
  3. 06 Ownership limits and entry conditions
  4. 07 Taxes, duties and incentives
  5. 08 Rule changes and their timeline
  6. 09 What the rules mean for demand, cost and route
  7. 10 How a foreign entrant should respond
  8. 11 Who's who
  9. 12 Methodology and sources

The full report is available to subscribers and buyers. The executive summary above is free to read.

Key questions

Which Malaysian location has the best site screen for a new data-centre campus?

Johor (Sedenak, Kulai, Iskandar Puteri) scores highest in KIRA's site screen at 3.4 out of 5, ahead of Selangor Cyberjaya at 3.2, according to KIRA's 2026 regulatory landscape analysis (Kira estimates).

Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

What is the foreign equity cap for a network facility in Malaysia?

Foreign equity in an individual NFP or NSP network licence is capped at up to 49%, with at least 30% bumiputera ownership, according to KIRA's 2026 regulatory landscape analysis (Skrine 2024; MCMC ASP(C) 2022).

Source: Skrine 2024, 2024 · KIRA report: Malaysia data centres 2026: regulatory landscape

Can a foreign company fully own a data centre in Malaysia?

A foreign company can hold 100% of a colocation or wholesale data centre through a wholly owned local company, according to KIRA's 2026 regulatory landscape analysis (Skrine 2024).

Source: Skrine 2024, 2024 · KIRA report: Malaysia data centres 2026: regulatory landscape

How large is the tax allowance for digital infrastructure investment in Malaysia?

The DESAC scheme gives a 100% investment tax allowance on qualifying capex, up to 100% of statutory income for up to 10 years, with applications open to 31 Dec 2027, according to KIRA's 2026 regulatory landscape analysis (MIDA DESAC 2024).

Source: MIDA DESAC 2024, 2027 · KIRA report: Malaysia data centres 2026: regulatory landscape

How much water has Malaysia approved for data centres?

Malaysia has approved 445.04 MLD of water for data centres to 2030, of which 63.9 MLD was in use in June 2026, according to KIRA's 2026 regulatory landscape analysis (The Star Oct 2026).

Source: The Star Oct 2026, 2030 · KIRA report: Malaysia data centres 2026: regulatory landscape

How much power will data centres in Johor need by 2030?

Johor's projected 2030 data-centre peak demand is 4428 MW, the largest of any state, according to KIRA's 2026 regulatory landscape analysis (PETRA via Bernama 2026).

Source: PETRA via Bernama 2026, 2030 · KIRA report: Malaysia data centres 2026: regulatory landscape

How many approved data-centre projects in Malaysia are not yet operating?

62 of 117 approved data-centre projects in Malaysia are not yet operating, so capacity is rationed rather than scarce, according to KIRA's 2026 regulatory landscape analysis (W.Media Oct 2026).

Source: W.Media Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

How much data-centre power has Malaysia approved?

Malaysia has approved 12.3 GW of data-centre grid capacity as of August 2026, against a projected 8.39 GW peak in 2030, according to KIRA's 2026 regulatory landscape analysis (The Star Oct 2026).

Source: The Star Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

How much of Malaysia's approved data-centre power is actually drawn?

Data centres drew 1.37 GW in August 2026, about 11% of the capacity already approved, according to KIRA's 2026 regulatory landscape analysis (The Star Oct 2026; PETRA via Bernama 2026).

Source: The Star Oct 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

What service tax applies to data-centre rentals in Malaysia?

Rental of space and servers is subject to service tax at 6% from 1 January 2026, down from 8% in July to December 2025, according to KIRA's 2026 regulatory landscape analysis (PwC MTB 2026).

Source: PwC MTB 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

What electricity price does a data centre face in Malaysia?

The ultra-high voltage tariff averages about 60 sen per kWh for a data centre, and 58-70 sen at a low load factor, according to KIRA's 2026 regulatory landscape analysis (analyst estimates; Malay Mail Sep 2026).

Source: Malay Mail Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

When is Johor's water-cooling pause expected to lift?

Johor's water-cooling pause is expected to lift in mid-2027, and only with reclaimed water, according to KIRA's 2026 regulatory landscape analysis (Johor state committee statement).

Source: KIRA research, 2027 · KIRA report: Malaysia data centres 2026: regulatory landscape

What local-content share must a data-centre approval meet?

A data-centre approval must reach at least 30% local domestic content, reported every six months to the task force and MIDA, according to KIRA's 2026 regulatory landscape analysis (Bernama Sep 2026).

Source: Bernama Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

What renewable-energy share will data centres in Malaysia need?

The green-power rule requires at least 30% renewable energy on total demand capacity for data centres, but the framework is still being drafted, according to KIRA's 2026 regulatory landscape analysis (Energy Commission).

Source: KIRA research, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape

How many approval gates must a data-centre project in Malaysia pass?

A data-centre project in Malaysia must pass five gates, held by at least six bodies federal and state, according to KIRA's 2026 regulatory landscape analysis (Kira estimates).

Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: regulatory landscape