Key questions
How much data-centre capacity will Malaysia have by 2030?
On today's path Malaysia reaches 4.5-5.5 GW of data-centre IT capacity by 2030, with 3.0-8.5 GW across four scenarios, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: trends and outlook
What is the 2030 data-centre capacity in the full-build scenario for Malaysia?
In KIRA's full-build scenario, Malaysia reaches 6.5-8.5 GW of operational IT capacity by 2030, against a power-queue scenario of 3.8-4.8 GW (Kira estimates scenario).
Source: Kira estimates, 2030 · KIRA report: Malaysia data centres 2026: trends and outlook
How much of Malaysia's approved investment in H1 2026 went to data centres?
Data centres and cloud took RM95.8 bn of the RM218.5 bn approved investment in Malaysia in January to June 2026, according to KIRA's 2026 trends and outlook analysis (MIDA H1 2026).
Source: MIDA H1 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much have hyperscalers announced for cloud investment in Malaysia?
Oracle announced USD 6.5 bn of cloud investment in Malaysia, with AWS at USD 6.2 bn, according to KIRA's 2026 trends and outlook analysis (Oracle Oct 2024).
Source: Oracle Oct 2024, 2024 · KIRA report: Malaysia data centres 2026: trends and outlook
How much rent do data-centre operators earn in Malaysia?
Leasing rent is the steadiest data-centre spend pool in Malaysia at USD 1.3-1.8 bn a year in 2026, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much data-centre capacity is live in Johor?
Johor had 1,110 MW of operational data-centre IT load in the first half of 2026, according to KIRA's 2026 trends and outlook analysis (C&W H1 2026).
Source: C&W H1 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much operational data-centre IT capacity does Malaysia have?
Malaysia's operational data-centre IT capacity was 522 MW in Q1 2025 and should reach 2,055 MW by end-2026, according to KIRA's 2026 trends and outlook analysis (Juwai Sep 2026).
Source: Juwai Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How many flagship data-centre projects has Johor approved?
The task force has approved 16 flagship data-centre projects in Johor and 10 in Selangor, cumulative to July 2026, according to KIRA's 2026 trends and outlook analysis (DCTF Sep 2026).
Source: DCTF Sep 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much is spent each year building data centres in Malaysia?
Construction and fit-out capex is the largest data-centre spend pool in Malaysia at USD 5-10 bn a year in 2026, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: Kira estimates, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How full is the Johor data-centre market?
Johor colocation vacancy is 0.7%, so its data-centre halls are close to full, according to KIRA's 2026 trends and outlook analysis (KF Atlas 2026).
Source: KF Atlas 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
What does Johor charge for water to data centres?
Johor set a data-centre water tariff of RM5.33 per cubic metre in August 2025, according to KIRA's 2026 trends and outlook analysis (Bernama Aug 2025).
Source: Bernama Aug 2025, 2025 · KIRA report: Malaysia data centres 2026: trends and outlook
What electricity price does a data centre pay in Malaysia?
A data centre pays about 60 sen per kWh on the ultra-high voltage tariff, against a 45.62 sen RP4 base tariff from July 2025, according to KIRA's 2026 trends and outlook analysis (TNB RP4 2024).
Source: TNB RP4 2024, 2025 · KIRA report: Malaysia data centres 2026: trends and outlook
When is Johor's water-cooling pause expected to lift?
Johor's water-cooling pause, set after Johor stopped Tier 1-2 approvals in November 2025, is expected to lift in mid-2027, according to KIRA's 2026 trends and outlook analysis (MITI Guidelines 2025).
Source: KIRA research, 2027 · KIRA report: Malaysia data centres 2026: trends and outlook
How long does a grid connection take for a data centre in Malaysia?
A grid connection takes 24-96 months from decision to service for a data centre in Malaysia, according to KIRA's 2026 trends and outlook analysis (Kira estimates).
Source: KIRA research, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
How much data-centre capacity is under construction in Malaysia compared with Thailand?
Malaysia had 1,039 MW of data-centre IT capacity under construction in H1 2026, against 859 MW in Thailand, according to KIRA's 2026 trends and outlook analysis (C&W H1 2026).
Source: C&W H1 2026, 2026 · KIRA report: Malaysia data centres 2026: trends and outlook
More on Data centres in Malaysia