Key questions
How much equity would a foreign company put into a Taiwan offshore wind stake?
KIRA's second horizon is a 20-30% stake in a 500 MW farm for US$200-350 mn of equity in 2027-2029, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2029 · KIRA report: Taiwan offshore wind 2026: trends and outlook
When should a foreign company decide on a lead bid for Taiwan offshore wind?
KIRA's gate for a lead bid on Round 3.4 needs workable rules and dated grid points, with the decision due in 2027, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2027 · KIRA report: Taiwan offshore wind 2026: trends and outlook
Which offshore wind stake should a Japanese or Korean company buy in Taiwan?
Buying a 20-30% stake in a financed or operating farm is a robust, do-now move for a Japanese or Korean company, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2026 · KIRA report: Taiwan offshore wind 2026: trends and outlook
How much offshore wind will Taiwan have by 2030?
About 4.8 GW was installed by June 2026, and awarded projects take Taiwan to 8.0-10.5 GW by 2030, a KIRA estimate against the 10.9 GW target, per KIRA's 2026 trends and outlook.
Source: Kira estimates; MOEA Jun 2026; Enerdata 2025, 2030 · KIRA report: Taiwan offshore wind 2026: trends and outlook
What could Taiwan offshore wind look like in 2030 if the grid and supply open up?
In KIRA's open and on-time future, Taiwan reaches about 10.5 GW by 2030, close to the 10.9 GW target, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2030 · KIRA report: Taiwan offshore wind 2026: trends and outlook
How fast is Taiwan's power demand planned to grow?
Taiwan's national power report 2026 plans demand growth of 2.5% a year over the next decade, up from 1.7% in the 2025 report, per MOEA power report 2026, according to KIRA's 2026 trends and outlook.
Source: MOEA power report 2026, 2026 · KIRA report: Taiwan offshore wind 2026: trends and outlook
How much debt does Fengmiao 1 carry?
Fengmiao 1 carries NT$103 bn of debt for 495 MW, per CIP Mar 2025 in KIRA's 2026 trends and outlook.
Source: CIP Mar 2025, 2025 · KIRA report: Taiwan offshore wind 2026: trends and outlook
What contract price would offshore wind buyers pay in an open-supply future?
In KIRA's open and on-time future, contract prices ease to NT$4.0-4.5 per kWh, and lead developers and foreign suppliers win, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2030 · KIRA report: Taiwan offshore wind 2026: trends and outlook
What contract price would offshore wind buyers pay if the build stalls?
In KIRA's stalled-build future, contract prices rise to NT$5.5 or more per kWh and 2030 capacity falls to 7.5-8.5 GW, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2030 · KIRA report: Taiwan offshore wind 2026: trends and outlook
What is the purchase floor for Round 3.3 offshore wind?
Round 3.3 adds a NT$2.29 per kWh purchase floor, per MOEA Mar 2026 in KIRA's 2026 trends and outlook.
Source: MOEA Mar 2026, 2026 · KIRA report: Taiwan offshore wind 2026: trends and outlook
What price did Round 3.1 corporate buyers pay for offshore wind power?
Round 3.1 corporate buyers signed at NT$5.0-5.5 per kWh, per Mirror Media 2024 in KIRA's 2026 trends and outlook.
Source: Mirror Media 2024, 2024 · KIRA report: Taiwan offshore wind 2026: trends and outlook
What does Round 3.3 need to pass in its selection score?
Round 3.3 needs 70 points out of 100 to pass, with 35 for developer record, 30 for financial capacity and 35 for project execution, per MOEA Mar 2026, according to KIRA's 2026 trends and outlook.
Source: MOEA Mar 2026, 2026 · KIRA report: Taiwan offshore wind 2026: trends and outlook
Will Taiwan's floating offshore wind pilots arrive on time?
Floating pilots slipping again beyond 2033 is KIRA's counter-case to its floating trend, rated high likelihood, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2033 · KIRA report: Taiwan offshore wind 2026: trends and outlook
What is the main delivery risk for a foreign offshore wind entrant in Taiwan?
A grid connection slipping a year or more is rated high likelihood and high impact for a foreign entrant, so KIRA suggests pricing the delay into bids, per KIRA's 2026 trends and outlook.
Source: Kira estimates, 2030 · KIRA report: Taiwan offshore wind 2026: trends and outlook
How much grid capacity does Taiwan's offshore phase 1 connect, and when?
The phase 1 offshore grid connects 7.64 GW by end-2027, and 1.5 GW a year is needed after that, per Taipower 2025 in KIRA's 2026 trends and outlook.
Source: Taipower 2025, 2027 · KIRA report: Taiwan offshore wind 2026: trends and outlook
More on Offshore wind in Taiwan