Key questions
How much would a foreign investor need to commit to an AI-ready data-centre option in Ho Chi Minh City?
KIRA's G2 capacity option for a 20-30 MW AI-ready phase with a partner in Ho Chi Minh City costs USD 140-240 million, gated on the grid date (KIRA estimates).
Source: Kira estimates, 2027 · KIRA report: Vietnam data centres 2026: trends and outlook
What is the high-growth scenario for Vietnam's data-centre capacity by 2030?
KIRA's sovereign AI corridor scenario reaches 750-900 MW of live capacity by 2030, the highest of its four futures (KIRA estimates).
Source: Kira estimates, 2030 · KIRA report: Vietnam data centres 2026: trends and outlook
What is the low-growth scenario for Vietnam's data-centre capacity by 2030?
KIRA's slow-lane scenario has 200-280 MW of live capacity by 2030, if power stays rationed and demand cools (KIRA estimates).
Source: Kira estimates, 2030 · KIRA report: Vietnam data centres 2026: trends and outlook
How fast is Vietnam's digital economy growing?
Vietnam's digital economy grew 17% to USD 39 billion in 2025, which keeps demand for data centres rising (KIRA 2026 trends and outlook, from e-Conomy 2025).
Source: e-Conomy 2025, 2025 · KIRA report: Vietnam data centres 2026: trends and outlook
How much has G42 committed to Vietnamese AI and cloud sites?
G42 backs three Vietnamese AI and cloud sites with up to USD 1 billion of consumption commitments (KIRA 2026 trends and outlook, from G42 Feb 2026).
Source: G42 Feb 2026, 2026 · KIRA report: Vietnam data centres 2026: trends and outlook
Which operator holds the most live data-centre capacity in Vietnam?
Viettel IDC holds 42 MW of live IT capacity in Vietnam, and VNPT holds 25 MW, as of October 2025 (KIRA 2026 trends and outlook, from CBRE Nov 2025).
Source: CBRE Nov 2025, 2025 · KIRA report: Vietnam data centres 2026: trends and outlook
How much have data-centre electricity bills risen in Vietnam?
Data centres were moved to the business electricity tariff, lifting their bills by more than 50% (KIRA 2026 trends and outlook, from TechNode Sep 2026).
Source: TechNode Sep 2026, 2026 · KIRA report: Vietnam data centres 2026: trends and outlook
What does a data centre cost to build per MW in Vietnam?
Building a data centre in Vietnam costs about USD 7.1 million per MW, and AI fit-out lifts that cost (KIRA 2026 trends and outlook, from Cushman Jul 2025).
Source: Cushman Jul 2025, 2025 · KIRA report: Vietnam data centres 2026: trends and outlook
How much live data-centre capacity could Vietnam have by 2030 in the baseline?
KIRA's baseline puts Vietnam's live data-centre IT capacity at 400-500 MW by 2030, about four times today (KIRA estimates).
Source: Kira estimates, 2030 · KIRA report: Vietnam data centres 2026: trends and outlook
How big is the annual rent pool for Vietnam's data centres in 2030?
KIRA estimates the baseline annual rent pool for Vietnamese data centres at USD 576-720 million in 2030.
Source: Kira estimates, 2030 · KIRA report: Vietnam data centres 2026: trends and outlook
How much named AI-ready data-centre capacity is at each stage in Vietnam?
Named projects hold 206 MW under construction, 240 MW approved or with land secured, and 550 MW at MoU or proposal stage (KIRA 2026 trends and outlook, from CBRE Nov 2025).
Source: CBRE Nov 2025, 2026 · KIRA report: Vietnam data centres 2026: trends and outlook
Where is Vietnam's live data-centre capacity located?
81% of Vietnam's live data-centre capacity sits in Hanoi and Ho Chi Minh City (KIRA 2026 trends and outlook, from CBRE Nov 2025).
Source: CBRE Nov 2025, 2025 · KIRA report: Vietnam data centres 2026: trends and outlook
How big is Vietnam's data-centre market in 2025?
Vietnam had 104 MW of live data-centre IT capacity in October 2025, the smallest base among the region's larger markets (KIRA 2026 trends and outlook, from CBRE Nov 2025).
Source: CBRE Nov 2025, 2025 · KIRA report: Vietnam data centres 2026: trends and outlook
What does a kW of data-centre capacity earn and cost each month in Vietnam?
A 42U rack at 5 kW lists at about USD 193 per kW a month, while power at the business tariff costs about USD 139 per kW a month (KIRA estimates, from rack listing 2025).
Source: Rack listing 2025; Kira estimates, 2025 · KIRA report: Vietnam data centres 2026: trends and outlook
When will Vietnam's data-centre power tariff be settled?
KIRA's signpost is a final data-centre tariff rule that puts technical load at the industrial rate, expected by Q2 2027 (KIRA estimates).
Source: Kira estimates, 2027 · KIRA report: Vietnam data centres 2026: trends and outlook