How a Vietnamese mobile operator buys tower site maintenance: one national programme, power first, and why newcomers lose
Summary
- A tower site is a power and access problem before it is a steel problem: in Typhoon Yagi 6,285 locations lost mobile contact because of power outages, and Viettel ran generators at 1,400 station locations. 1
- Operators in the region outsource site maintenance centrally for all sites, covering power, air-conditioning, earthing and security, rather than site by site. 2
- The towerco is a separate buyer's world: Viettel Construction owned 11,117 stations at end-August 2025 with a co-location ratio of 1.034, and operations made up about 51% of its first-quarter 2025 revenue. 3 4
- Contracts are won by tender or from pre-registered lists, run on short terms with extensions, and carry KPIs and fee deductions; the operator keeps a small in-house team to check the work. 5 6 7 8
- Outsiders lose on punctuality, skills for newer equipment and price-led bidders who subcontract after winning; switching is avoided and trials are common. 9 10 11
- The workload is growing: about 11,000 5G stations by mid-2025 against operators' plans for 20,000 and 10,000 more, a 2G shutdown on 16 September 2026, and a sharing agreement between VNPT and MobiFone that may change which sites get kept. 12 13 14
Transcript
01A tower site is a power problem
You buy site maintenance for a national mobile network. What should an outside contractor understand first?
That a tower site is mostly a power, cooling and access problem, and the steel is the easy part. When Typhoon Yagi hit the north in September 2024, 6,285 locations lost mobile contact, and the report put the cause on power outages. 1 Before the storm the operators had strengthened 284 generators, and one operator ran generators at 1,400 station locations. 1 That is the job in one picture: fuel, batteries, a technician who can actually reach the site. When operators in the region outsource site maintenance, the scope is exactly that list, power, air-conditioning, earthing and security. 2
So when a storm comes, what does the maintenance contractor do?
Restores power and clears the site. Look at what one operator reported by 8 September: 1,710 power-loss sites fixed, and about 500 repair teams with nearly 8,000 technical staff in the field. 1 I cannot tell you how many of those were contractors and how many were the operator's own people, that is not published and it differs by region. 8 What I can tell you is what I look at after a storm. Who answered the phone at night, who had fuel on the truck, who sent a person who knew the cabinet. Nobody remembers the contractor who was cheap in the tender. 9
02Operator and towerco are different buyers
Many outsiders assume the towerco does all the tower upkeep. Is that right?
Be careful, there are two buyers and they do not buy the same thing. The operator buys upkeep for the sites it runs. The towerco owns the structure and rents space on it. Viettel Construction, the biggest towerco, owned 10,350 stations at the end of March 2025 and said 340 of them were leased by more than 2 carriers. 4 By the end of August 2025 it had 11,117, with 187 added in that month alone. 3 How the upkeep is split between an operator and the tower owner is written into each lease and I will not pretend it is one rule. Ask each customer. 2
Does the towerco's own business tell you anything about the maintenance market?
A little. Operations were about 51% of that company's first-quarter 2025 revenue, the largest segment, on estimated revenue of 2,754.5 billion VND. 4 So running and maintaining networks is a big business inside the group, not an afterthought, and a foreign newcomer should assume the local specialist is hard to beat on its home ground. 15 Tenancy matters too. Its co-location ratio was 1.034 at end-August 2025, and 375 stations hosted 2 or more tenants. 3 A shared site has several customers who all want access, and every access visit becomes a coordination job. 8
03One national programme, not a site-by-site market
How is the work packaged when you buy it?
As a programme. Operators in the region told KIRA that site maintenance is outsourced centrally for all sites, not site by site. 2 That changes who can bid. A firm that is excellent in one province but cannot show a national structure will find it hard to be on the page at all. 15 What the central buyer wants is one accountable name per region, a rule for who does what, and a way to see every site on one screen. The trade-off is that the big programme hides weak provinces. Tell the truth about your weak provinces in the tender and I will respect you for it, even if you lose the tender. 5
How do you find and choose contractors?
By tender or from a list of contractors who have already been registered, and the decision sits with top management or a tender committee. 5 To get registered you show a track record. I know that sounds circular, a newcomer needs references before it can get references. 15 The way into the list is usually a small first package, in one region, where the regional operations manager is willing to vouch for you. That person is the one who gets the call in the middle of the night, so what he says counts. 7
04KPIs, penalties and renewal
What does the contract measure?
Regionally, infrastructure contracts carry KPIs and penalty clauses, with fee deductions when inspections fail, and the operator's own engineers monitor performance. 7 In my world the simple ones are the best: how fast you arrive, how long the site stays down, whether the same fault comes back. 7 Arrival and repair are two different numbers and I ask for both. A contractor who always arrives quickly and always leaves the fault half fixed looks good on one line and terrible on the other. 9
How long do contracts run, and what happens at renewal?
Short terms with extensions. 6 Fees are fixed for long periods, so the owner pushes for a lower price at each renewal as a reward for loyalty, and the contractor is squeezed when labour and material costs rise. 16 I have a lot of sympathy for contractors here. If the fee is fixed and the diesel and wages move, the contractor gets thinner every year, and a thin contractor stops sending the second technician. A buyer who squeezes at every renewal usually gets it back in service quality. 16
05Why outsiders lose
Where do contractors fall short in your experience?
Punctuality, skills and newer equipment. Those are the standard complaints I hear across the region: late arrival, the wrong skill set for the job, and no ability to service newer electronic systems. 9 A technician who can fix a diesel generator but is lost in front of a modern rectifier cabinet is a problem the day it happens. 9 The other thing is the bidder who is not what he says. Small electrical and air-conditioning firms win on price although they are not full service providers, and some who call themselves integrated simply subcontract after winning. 10 Then my contract is really with the subcontractor, and I never met him. 10
Does it matter who you know?
It does, and I will not pretend otherwise. Business connections strongly influence who wins. 17 Contractors also lose technicians to each other for small pay differences, so the person I trusted last year may be at a competitor this year. 17 That is why we avoid switching. A new provider disrupts daily operations, so we often run a trial period before we sign. 11 A foreign firm that offers a trial in one region at a fair price is more convincing than a firm that offers a big discount for the whole country. 11
065G, sharing and the 2G switch-off
What is changing the workload for site maintenance now?
Three things. First, 5G. By mid-2025 operators had about 11,000 5G stations, equal to 7.7 per cent of existing 4G stations, and one operator aimed to add 20,000 that year while another planned 10,000 more. 12 More equipment means more power, more cooling and more cabinets. 18 Second, the 2G shutdown took effect on 16 September 2026, which frees spectrum for 4G and 5G, and 5G subscriptions had risen to 27.2 million by August. 13 Every old cabinet that is switched off is either removed or kept, and somebody must decide which, site by site. 18
And the third?
Sharing. VNPT and MobiFone have signed a memorandum of understanding to share 4G and 5G infrastructure nationwide, and in many cities operators often run 3 or 4 stations in the same area. 14 5G may need 3 to 5 times as many stations as earlier generations, so sharing is attractive. 14 I would not plan around it yet, the same article cites no binding rule. 14 For a maintenance contractor this means the map of sites will change under you. Sites get merged, kept or removed, and a contract written for the old map will have arguments about the new one. Maintenance spending rises with ageing assets and network expansion anyway. 18
07Advice to a newcomer, and what worries me
A Japanese or Korean facilities-management firm wants to supply tower sites in Vietnam. What should it do?
Start small, in one region, with power and cooling, and be the contractor who answers at night. 9 Expect the operator to keep a small in-house team to check your work, and treat that team as your customer, not your enemy. 8 Do not lead with a discount for the whole country. Registration and track record decide, and a trial is how we get comfortable. 15 11
What would change your mind, and what worries you?
I would change my mind about foreign newcomers if one showed me a full year of site records from a neighbouring market, with both arrival times and repair times, and a plan for what happens when its technicians are poached. 17 7 What worries me is the next storm. Last time the failure was power, with 6,285 locations out of contact. 1 Operators are adding stations, and the towerco keeps adding sites too, 1,117 so far in 2025 by end-August. 3 More sites, a fixed fee and a thinner contractor is the combination that fails first. 16
Sources and basis
- 1VnEconomy, 9 Sep 2024, on Typhoon Yagi (storm No. 3) in September 2024: 6,285 locations lost mobile contact because of power outages; telcos had strengthened 284 generators before the storm; Viettel's disaster-prevention app ran generators at 1,400 mobile station locations; by 8 September Viettel had fixed 1,710 power-loss sites; about 500 Viettel repair teams with nearly 8,000 technical staff were deployed; 27 telecom poles toppledPublic source · VnEconomy, 9 Sep 2024 · link
- 2Mobile operators outsource tower site maintenance centrally for all their sites; the scope is air-conditioning, power, earthing and securityKIRA field interviews · KIRA field interviews, Malaysia telecom operators
- 3Broker reports (HSC dated 29 Sep 2025, Vietcap dated 12 Sep 2025) summarised by Elibook, 9 Oct 2025: CTR had 11,117 BTS stations at end-August 2025, up 1,117 year to date, with 187 added in August; co-location ratio 1.034; 375 stations host 2 or more tenantsPublic source · Elibook, 9 Oct 2025 (reporting HSC and Vietcap) · link
- 4Viettel Construction (CTR), reported by Tạp chí Công Thương, 16 Apr 2025: owned 10,350 BTS stations at end of March 2025 and calls itself Vietnam's No. 1 TowerCo; 340 stations leased by more than 2 mobile carriers; co-location ratio 1.03; operations (vận hành khai thác) were about 51% of its Q1 2025 revenue, the largest segment, on estimated Q1 2025 revenue of 2,754.5 billion VND; 2025 targets of 2,000 new BTS locations, at least 300 stations with customers outside Viettel Group and a co-location ratio of 1.045Public source · Tạp chí Công Thương, 16 Apr 2025 · link
- 5Contractors are chosen by open tender or from pre-registered vendor lists, and top management or a tender committee decidesKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 6Contract terms are short, with extensions agreed at renewalKIRA field interviews · KIRA field interviews, Malaysia telecom and infrastructure operators
- 7Infrastructure contracts carry KPIs and penalty clauses, with fee deductions when inspections fail; performance is monitored by the operator's own engineering teamKIRA field interviews · KIRA field interviews, Malaysia infrastructure operators
- 8Even when outsourcing, owners keep a small in-house team to supervise contractor qualityKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 9Common complaints about contractors are poor punctuality, the wrong skill sets and inability to service newer electronic systemsKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 10Small electrical and air-conditioning firms win tenders on price despite not being full service providers, and some self-styled integrated players subcontract the work after winning the dealKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 11Switching contractors is avoided because a new provider disrupts daily operations; trial periods are common before signingKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 12Viet Nam News, 8 Jul 2025, quoting the Authority of Radio Frequency Management: about 11,000 5G base stations by Viettel, VNPT and MobiFone, equal to 7.7 per cent of existing 4G stations, covering about 26 per cent of the population; Viettel aimed to install 20,000 5G base transceiver stations in 2025; MobiFone planned to add 10,000 base stationsPublic source · Viet Nam News, 8 Jul 2025 · link
- 13Viet Nam News, 24 Sep 2026: 2G shutdown took effect on 16 September 2026, except in Trường Sa, Hoàng Sa and the DK1 offshore platforms, freeing the 900MHz and 1,800MHz bands for 4G and 5G; 5G subscriptions rose from more than 14 million (September 2025) to 27.2 million (August 2026); 273 villages remain without adequate mobile coveragePublic source · Viet Nam News, 24 Sep 2026 · link
- 14Viet Nam News, 10 Jul 2026: VNPT and MobiFone signed a memorandum of understanding to share 4G and 5G infrastructure nationwide; in many major cities operators often run three or four (3 or 4) base transceiver stations in the same area; 5G may need three to five (3 to 5) times as many base stations as earlier generations; the Ministry of Science and Technology is encouraging Viettel and VNPT to share infrastructure with smaller operators; the article cites no binding rulePublic source · Viet Nam News, 10 Jul 2026 · link
- 15Pre-registration with the operator or the relevant ministry is a gate to work in a sector; a track record decides tendersKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 16Fees are fixed for long periods, so owners push for lower prices at each renewal as a reward for loyalty; fixed fees squeeze contractor margins when labour and material costs riseKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 17Business connections strongly influence who wins contracts; technicians move between firms for small pay differences, so staff turnover is a constant cost for contractorsKIRA field interviews · KIRA field interviews, Malaysia facilities management
- 18Maintenance spending rises with asset ageing and network expansionKIRA field interviews · KIRA field interviews, Malaysia telecom and infrastructure operators